1 / 17

Defence Project Management 2007

Defence Project Management 2007. Learning to love project risk management Dr Andrew Tyler DG Ships, DE&S. Defence projects – more risky than most. Military superiority Complexity risk Technology maturity risk Complex procurement strategies (multi-party, multi-national etc.)

shayla
Télécharger la présentation

Defence Project Management 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Defence ProjectManagement 2007 Learning to love project risk management Dr Andrew Tyler DG Ships, DE&S

  2. Defence projects – more risky than most • Military superiority • Complexity risk • Technology maturity risk • Complex procurement strategies (multi-party, multi-national etc.) • Complex market context • Politics

  3. Defence project risk management • Project management & risk management are synonymous • The risk - to what….? • Risk, issues, and uncertainty • Risk perception • Expressing risks • Risk management actions • Quantifying risks • Linking risks and project forecasting

  4. The risk to what……? • The risk to what? • Business objectives, safety, financial targets etc. etc. • Express risk impact in the right currency • £££s, time delay, lost time accidents etc. etc.

  5. Risk, issues, and uncertainty “….as we know, there are known unknowns; there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we do not know. But there are also unknown unknowns – the ones we don’t know we don’t know.” Donald Rumsfeld

  6. Identifying a risk • A risk is an event or situation with a realistic likelihood of occurring and an unfavourable consequence should it occur – the known unknowns • If you don’t know what it is, it’s an uncertainty – the unknown unknowns • If it has occurred already, it is an issue – known knowns • Risks can be specifically identified and quantified in the appropriate currency

  7. Risk perception • Dogs risk management in many fields - especially public perception of risk • Less so in project risk management but; • High impact, low probability risks (usually dramatic and eye-catching) usually over-stated subjectively and understated quantitatively

  8. Expressing risks • Specificity is key; “There is a risk we could lose key staff” • Cause-effect-consequence “There is a risk that the hot market for software engineers may result in loss of senior software designers leading to delay in completing our system design review on time” 

  9. Risk management actions • Specificity is key • Assigned to a single responsible individual • Specific action(s) achievable within a realistic period (6-12months) “HR manager to implement golden handcuffs scheme within 3 months” • Can sometimes be a good way of testing risk expression

  10. Quantifying risks • A very tricky area – but essential • Computer models can be very misleading; • Statistical approaches often suppress high impact, low probability risks • Risk envelope often too tight at outset – risky projects with only 5-10% difference between 10% and 90% probabilities of out-turn • Risk inter-dependencies often not well handled • Risks to schedule are almost always risks to cost – easy to count twice • ‘Black box’ nature often leads to mistakes • Ability to run models regularly is essential

  11. Managing the project risks • The project team is there for one reason only – to manage risks • If it weren’t for the risks, the project team would consist of a contracts officer…..and that’s all • What matters is how the risks are identified, quantified and managed • The movement in the risk profile is the heartbeat of the project – no movement, no life

  12. Risk mitigation planning Project milestone deliveries Initial Risk Envelope Zero risk Late emerging risk and mitigation Early stage risk identification Linking risk to project forecasting PESSIMISTIC Project Performance Metric e.g. time, cost Project End MOST PROBABLE OPTIMISTIC Time

  13. Evidence of active risk management?

  14. New risk(s) identified Risk mitigation in place Note risk asymmetry Project re-approval – risks reassessed Risk ‘funnel’ reducing Evidence of active risk management?

  15. Opportunity management • An opportunity; • A situation or circumstance with a realistic likelihood of occurring, and which provides a potential benefit • Mature risk management embraces risks and opportunities equally

  16. CVF risk and opportunity management • Early introduction of Earned Value Management • Discipline of work breakdown structure and single point responsibility established (Cost Account Manager) • Every CAM owns quantified risk and opportunity against base cost/time • Held in central model - rolled up monthly to provide holistic project performance forecast

  17. Defence project risk touchstones • Centralised risk systems with hundreds of risks are unmanageable unless highly federated with single-point-of-accountability • Specificity in risk expression and actions • Quantification of risk is a minefield – beware! • Project forecasts should be moving constantly against the changing risk/opportunity profile • Risk and opportunity should be treated as equals • In a Department of State, political risks are rarely treated honestly

More Related