1 / 14

Jacksonville Harbor Deepening: A Never Ending Saga

Jacksonville Harbor Deepening: A Never Ending Saga. Quinton White , Jr ., Ph.D. Professor of Biology and Marine Science Executive Director, Marine Science Research Institute Jacksonville University. St. Johns River – Mouth to Jacksonville - 1791.

shlomo
Télécharger la présentation

Jacksonville Harbor Deepening: A Never Ending Saga

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jacksonville Harbor Deepening: A Never Ending Saga Quinton White, Jr., Ph.D. Professor of Biology and Marine Science Executive Director, Marine Science Research Institute Jacksonville University

  2. St. Johns River – Mouth to Jacksonville - 1791

  3. Jacksonville Harbor Channel Improvements – First Dredging • Dredging of the 6 mile long channel commenced in June 1892 and took exactly two years. • The 15 foot deep channel permitted ships drawing 20 feet to dock in Jacksonville. • Prior to project completion, discussion about additional deepening commenced.

  4. Jacksonville Harbor Channel Improvements – Deepening • After 6 years of deliberation (1902)Congress made an initial appropriation of $350,000 to start the dredging of a channel 24 feet deep and 300 feet wide, from Jacksonville to the sea. • By 1906 the work was completed and the 24-foot channel became a reality. • Ten years later, in 1916, another dredging project was started that resulted in a 30-foot channel from Jacksonville to the sea. • By 1924 ships weighted to 30 feet could dock at the municipal docks in Jacksonville at low tide. • Total cost of dredging and jetties: $7 million

  5. Port of Jacksonville Project and Channel Improvements • 1880 – June; Jetties at entrance (maintenance only) • 1890 –Two jetties on Volusia Bar and 6’ deep channel • 1892- Secure 15’ deep navigational channel Dames Pt (RM 11) to Mile Point (RM 5) - Completed 1894 • 1896 – 24’ Jacksonville to Ocean & extend jetties - completed 1906 • 1910 – 30’ Jacksonville to Ocean – completed in 1916 • 1925 – The distance from the mouth to the FEC RR Bridge is 28.1 miles • 1930 - Widen bend at Dames Point to 900’ • 1935 - Widen Trout, Six Mile and Drummond creeks • 1945 – The river channel deepened to 34’ and the Dames Pt. Fulton Cut made – Federal Project 26.8 miles long. • 1965 – 38’ deepening completed in 1978 • 1998-2004 – RM 15 to mouth of the SJR deepened to 40’ • 2010 – Drummond Pt. to Tallyrand (5.3 mi) from 38 to 40’

  6. St. Johns River Dredging at Dames Point

  7. 1918

  8. St. Johns River Dredging Impacts: • Impact to benthic (bottom dwelling) organisms • Impact to salinity zones • Impact to marine mammals • Impact to flushing rates ( positive and negative) • Impacts to tributaries (positive and negative)

  9. Mitigation • Very Difficult to Mitigate Salinity Changes • Corps had proposed to increase monitoring • The proposed monitoring has no mechanism to react if damage is discovered. • Monitoring is not Mitigation • Purchase of Credits from Wetland Mitigation Banks • Funding Nutrient Reductions that are already existing regulatory requirements • Restoration of the Ocklawaha River (removal/breaching of the Rodman Dam) has been withdrawn as an option

  10. The Billion Dollar Question: Is it worth it economically for the environmental damage that will occur? And is there a better way to achieve the same end result?

More Related