html5-img
1 / 14

E1. Admission Flow – Similar to Coffee Shop

E1. Admission Flow – Similar to Coffee Shop. Marshall provides higher education to executives and receives about 1000 applications per month. The evaluation starts with a preliminary classification:

skah
Télécharger la présentation

E1. Admission Flow – Similar to Coffee Shop

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. E1. Admission Flow – Similar to Coffee Shop • Marshall provides higher education to executives and receives about 1000 applications per month. The evaluation starts with a preliminary classification: • Group A: Applicants with desired recommendations, working experience, etc. (50% of the applicants) • Group B: Other applicants. (50% of the applicants) • Applicants in group A will be further considered through an advanced review. Applicants in group B will be rejected. • On average there were are 200 applications in the preliminary review stage, and 100 applications in the advanced review stage • a) How long does group A spend in the application process? • b) How long does group B spend in the application process? • c) How long is the average process time?

  2. E1. Difference Between R and I • Throughput is 1000 per month, inventory in the first process is 200. • Lets assume a month is 30 days. Then I can state: R=1000/30 = 33.33 per day but  I in the first process is still 200. • Now suppose a day is 8 hours. Then I can state: R= 33.33/8 = 4.167  per hour but  I is still 200.​ • I can also state: R=4.167/60 =0.0694   per minutes but  I is still 200.​ • Assuming a year to be 12 month, R = 12000 per year, but  I is still 200.​ • In all these cases, Inventory in processes  A and B are 200 and 100, respectively.

  3. E1. Admission Flow Accept Process 100 50% 1000 200 Reject Process 50% a) How long do the applicants spend in the preliminary stage? RT=I  T = I/R=200/1000 = 0.2 month Applicants spend 0.2(30) = 6 days in the first stage Applicants from group B receive an answer in 6 days on average

  4. E1. Admission Flow • b) How long do the applicants from group A spend in the advanced review stage? I =100 , R = 1000(0.5) = 500 TR= I  T=I/R  T= 100/500 = 0.2 Applicants from group A spend 0.2(30) = 6 days on average in the advanced review stage. Applicants from group A receive answer in 12 days (6 + 6) on average.

  5. E1. Admission Flow • c) What is the average processing time? • 0.5(6)+0.5(12) = 9 days • Is there an alternative way to calculate the average waiting time? Do it------ Little’s Law holds for complicated systems.

  6. E2. Bank Loan – The Same as the Previous Example • Bank XYZ receives 20 loan requests per hour on average. Each loan request goes through an initial processing stage, after which an “accept or reject” decision is made. Approximately 80% of the loans are accepted, and these require additional processing. Rejected loans require no additional processing. Suppose that on average 5 loans are in the initial processing stage, and 25 (accepted) loans are in the additional processing stage. Accept 80% • What is the average processing time required for a loan • What is the average processing time required for a rejected loan? • What is the average processing time required for an accepted loan (including the initial processing stage)? 25 20 5 Reject 20%

  7. E2. Bank Loan a) What is the average processing time required for a loan request? R = 20 loans/hour I = 5+25 = 30 loans Average processing time = Throughput Time RT= I  T = I/R = 30/20 = 1.5 hours b) What is the average processing time required for a rejected loan? R = 20 loans/hour I = 5 loans Average processing time = Throughput Time RT= I  T = I/R = 5/20 = 0.25 hours

  8. E2. Bank Loan c) What is the average processing time required for an accepted loan (including the initial processing stage)? Initial Stage: As computed for rejected applications the time for the initial process is T = I/R = 5/20 = 0.25 hours Additional Processing Stage: R = 20 × 0.8 = 16 loans/hour, I = 25 loans T = I/R = 25/16 = 1.5625 Average Total Processing Time = = 0.25 + 1.5625 = 1.8125 hours

  9. E3. Fresh Juice and Fruit • Consider a roadside stand that sells fresh oranges, and fresh orange juice. Every hour, 40 customers arrive to the stand, and 60% purchase orange juice, while the remaining purchase oranges. Customers first purchase their items. Customers that purchased oranges leave immediately after purchasing their oranges. Any customer that ordered orange juice must wait while the juice is squeezed. There are 3 customers on average waiting to purchase either oranges or orange juice, and 1 customer on average waiting for orange juice to be squeezed. 40 0.6(40) = 24 3 1 How long on average must customers that purchase fresh orange juice wait?

  10. E3. Fresh Juice and Fruit • How long on average must customers that purchase fresh orange juice wait? • In the ordering process • RT =I  40T = 3  • T = 3/40 hours  T = 60(3/40) = 4.5 minutes • In the juice squeezing process • RT =I  24T = 1  • T = 1/24 hours  T = 60(1/24) = 2.5 minutes • Average waiting time = T = 4.5 + 2.5 = 7 minutes 40 24 3 1

  11. E4. Call Center • 3. A call center employs 1000 agents. Every month 50 employees leave the company and 50 new employees are hired. • a) How long on average does an agent work for this call center? •  Now suppose the cost of hiring and training a new agent is $1000. The manager of this call center believes that increasing agents’ salary would keep them working longer term in the company. The manager wants to increase the average time that an agent works for the call center to 24 months, or 2 years. • b) If an agent works for the call center for 24 months on average, how much can the company save on hiring and training costs over a year? Hint: first determine the current annual cost for hiring and training, then determine the new annual cost for hiring and training. • c) How much the monthly salary of each agent can be increased?

  12. 1000 Agents 50/month 50/month E4. Call Center a) How long on average does an agent work for this call center?   R = 50 people/month I = 1000 people Average working time = Throughput Time = I/R = 1000/50 = 20 months or 20/12 = 1.67 years Suppose the cost of hiring and training a new agent is $1000. The manager of this call center believes that increasing agents’ salary would keep them working longer term in the company. The manager wants to increase the average time that an agent works for the call center to 24 months, or 2 years.

  13. E4. Call Center b) If an agent works for the call center for 24 months on average, how much can the company save on hiring and training costs over a year? Hint: first determine the current annual cost for hiring and training, then determine the new annual cost for hiring and training. 1000 Agents 1000 Agents ?/month 50/month ?/month 50/month Current annual cost for hiring and training: Throughput Rate = 50 people/month = 600 people/year Annual hiring and training cost is 600 (1000) = $600,000 20 months 2 years

  14. E4. Call Center New annual cost for hiring and training: Average working time = Throughput Time = 24 months = 2 years Throughput Rate  R= I/T = 1000 people / 2 years = 500 people/year  41.7 per month Annual hiring and training cost is 500 (1000) = $500,000 Annual saving on hiring and training cost is $600,000-$500,000 = $100,000 c) How much the monthly salary of each agent can be increased? Average # of employees = 1000 Annual saving on hiring and training cost = $100,000 Monthly saving = $8,333.33 8333.33/1,000 = $8.33 per employee/month

More Related