TFTR D&D Status July 24, 2001

TFTR D&D Status July 24, 2001. Project Status. The TFTR D&D Project will be completed on time and within budget. Project Status. Reviews since 12/00: • DOE Cost and Schedule Review, 12/00 • PPPL Audit of D&D Project, 12/00 - 1/01 - no findings

starbuck
Télécharger la présentation

TFTR D&D Status July 24, 2001

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TFTR D&D Status July 24, 2001

  2. Project Status The TFTR D&D Project will be completed on time and within budget

  3. Project Status Reviews since 12/00: • DOE Cost and Schedule Review, 12/00 • PPPL Audit of D&D Project, 12/00 - 1/01 - no findings • DOE-PG Unified Safety Review, 4/01 - no findings • DOE-CH Review of Sector Lift Procedure, 5/01 - approved • ALARA Review of Vessel Segmentation, 5/01 - approved • DOE EH-24 Review, 5/01 - awaiting report

  4. Project Statuscont Engineering: • Vessel Segmentation FMEA approved • Successful Final Design Review for Vessel Segmentation • Last of the removal procedures are being prepared • Temporary vessel supports, for vessel segmentation, have been designed, fabricated, tested, and are currently being installed

  5. Project Statuscont Engineering cont: • A sector disassembly fixture has been designed, fabricated and tested - a second fixture is currently in fabrication

  6. Project Statuscont Engineering cont: • A special vertical bandsaw has been tested and procured for cutting the TF coils in half to reduce the cost of shipping them for burial • Contamination barriers for the annulus between the vacuum vessel and the TF coils have been designed, tested, and are currently being installed

  7. Project Statuscont Engineering cont: • Continuing to spend more time on engineering (especially Diamond Wire Cutting) because it improves overall safety and efficiency • Continuing to pay attention to the principles of Integrated Safety Management

  8. Project Statuscont Diamond Wire Cutting Engineering: • Cutting of the vacuum vessel will be done using a diamond wire rope technology that has been specifically developed for this purpose - reduced airborne contamination - reduced worker exposure - reduced cost

  9. Project Statuscont Diamond Wire Cutting Engineering cont: • When each vessel segment is removed, two TF coils will be lifted with it • A disassembly fixture will be used to support the vessel segment while the TF coils are rotated off of it • The vessel segments will be placed in special shipping/burial containers and immediately shipped • A special vertical bandsaw will be used to cut the TF coils in half to reduce the cost of shipping them for burial

  10. Project Statuscont Diamond Wire Cutting Engineering cont: • Diamond Wire Cutting trials have developed the process into a mature state • Results indicate that we can do a through-cut in a day • Process has been refined to reduce the chance of a broken wire and reduce worker exposure should a wire need to be replaced • Process for gas cooling/cleaning of the wire has been developed to reduce tritium contaminated waste

  11. Project Statuscont Diamond Wire Cutting Engineering cont:

  12. Project Statuscont Field Work: Vacuum Pumping Ducts have been removed

  13. Project Statuscont Field Work cont: Lintels and columns and Shear Compression Panels have been removed

  14. Project Statuscont Field Work cont: Ducts connecting Neutral Beamlines to the vacuum vessel have been removed

  15. Project Statuscont Field Work cont: Vacuum vessel appendages have been removed and all windows have been reinforced

  16. Project Statuscont Field Work cont: Vacuum vessel has been filled with lightweight concrete

  17. Project Statuscont The TFTR D&D Project is continuing on a path which will assure that it will be completed on time and within budget

  18. FY01 Accomplishments

  19. FY01 Remaining

  20. FY02 Planned

  21. Radwaste Status