1 / 16

Optimisation of New Build Spent Fuel Management and Disposal

Optimisation of New Build Spent Fuel Management and Disposal. Peter Haslam Public Policy Advisor Nuclear Industry Association 25 January 2011. Structure of Presentation. Overview of Government Spent Fuel Management “base case”

storm
Télécharger la présentation

Optimisation of New Build Spent Fuel Management and Disposal

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Optimisation of New Build Spent Fuel Management and Disposal Peter Haslam Public Policy Advisor Nuclear Industry Association 25 January 2011

  2. Structure of Presentation • Overview of Government Spent Fuel Management “base case” • Outline of work carried out with NDA to identify opportunities and feasibility of optimising the “base case” • Initial results of preliminary scoping studies with NDA

  3. Spent Fuel Generation • 60 years operation would generate a total of approximately 3,400 assemblies per EPR, including time for planned outages • Each Spent Fuel Assembly contains approximately 530kg Uranium • A Single EPR will produce approximately 1800tHM over 60 years of operation

  4. RWMD assumptions related to New Build Spent Fuel Inventory • RWMD will publish a Disposal System Safety Case. This will provide safety arguments supported by illustrative disposal concepts for three geological environments. • The DSSC considers the MRWS Baseline Inventory and an upper inventory scenario which includes wastes and SF arising from a new nuclear build power programme • The upper inventory scenario assumes construction of four AP1000 and four UK EPR corresponding to a generating capacity of 10 GW(e) which leads to an inventory of 13,000tHM of spent fuel (assumed 60 year operating lives) • The illustrative disposal concepts assume use of high integrity disposal canisters (each holding four SFA) • The DSSC recognises that the disposal concepts will not be chosen until future stages

  5. Spent Fuel Spent Fuel Initial Spent Fuel Cooling Spent Fuel Interim Storage Spent Fuel Encapsulation Final Disposal Transfer Underwater Assemblies SFA loaded into Spent Fuel storage of spent Transfer of spent Spent Fuel stored Encapsulation of Off - Site transferred to transport flasks for removed from fuel in reactor fuel fuel to Interim for period of up to spent fuel for Transport to GDF Geological reactor fuel transfer to reactor pool for initial Storage Facility 100 years disposal Disposal Facility pool encapsulation plant . cooling Spent fuel encapsulation On - site Spent Fuel Interim Storage facility Reactor fuel pool Facility The Spent Fuel Management Case Base • Cooling in reactor fuel pool 2-10 yrs • Transfer to on-site Spent Fuel Interim Storage Facility • Store for around 100 years post discharge from reactor for temperatures to fall to meet GDF temperature constraints of bentonite buffer material • Transfer to an encapsulation facility • Encapsulation of long-stored fuel in KBS3 copper containers (maximum 4 fuel assemblies) • Transfer to GDF for disposal (new-build emplacement after c.2130)

  6. Optimisation of Base Case • Current strategy safe, practical and deliverable • Opportunities to optimise certain aspects • Storage periods • Storage Arrangements • Encapsulation facility/facilities • Optimisation of current reference disposal conceptual design • Consideration of other disposal concepts • ILW Management – Scheduling • NDA RWMD was contracted by NIA to identify issues and options that could result in opportunities for optimisation

  7. Working with NDA-RWMD • RWMD has undertaken work commissioned and fully funded by the Nuclear Industry Association • Scope: • Investigate the feasibility of and issues associated with storage and encapsulation plants for spent fuel • Investigate issues with alternative transport and disposal package types • Identify issues and options that could result in the optimisation of the GDF concept to meet the characteristics of both legacy and new build waste • Investigate the potential benefits of alternative disposal concepts

  8. Published November 2010 NDA website http://www.nda.gov.uk/documents/upload/Geological-Disposal-Feasibility-studies-exploring-options-for-spent-fuel-from-new-nuclear-power-stations-November-2010.pdf RWMD Report

  9. RWMD initial disposability assessment indicated cooling period of the order of 100 years required before disposal Based on temperature constraint on bentonite backfill New work indicates above ground storage period could be reduced to around 50 years by judicious mixing of long cooled and short cooled fuel Other feasible options which also permit earlier emplacement include: Smaller diameter canisters with reduced heat load, or Undertake research on the temperature limit in the bentonite buffer Spent Fuel Interim Storage period

  10. Base case assumes one store per site and on-site storage post decommissioning until GDF is available and fuel is sufficiently cooled Advantages that each site manages its own waste Disadvantage in duplication of facilities each of which will require safety and security infrastructure Centralised storage could reduce overall costs and allow complete early clearance of multiple sites Fuel Handling and Centralised Storage (1)

  11. Fuel Handling and Centralised Storage (2)

  12. Encapsulation of spent fuel into form suitable for final disposal Base case assumes: Use of copper canister concept Packaging at reactor site with transport to GDF Encapsulation plant is complex and expensive facility Swedish concept assumes single encapsulation plant and centralised storage UK legacy fuel also requires encapsulation Opportunities to share facility between legacy and new build or between new build operators Encapsulation

  13. Use of alternative containers in reference concept GDF Larger casks with more SFA = higher thermal loading Considers viability of a single Multi-Purpose Container (MPC) for storage – transport – disposal Could remove need for repackaging and additional handling of fuel Existing designs of MPC would require significant up rating and redesign of GDF infrastructure and handling systems Conceptually a smaller MPC could be designed for increased compatibility with geological disposal and UK transport infrastructure Further work needed to justify early sealing of SF in the container and ability to make future transport and disposal safety cases Alternative Disposal Pakages

  14. Alternative Disposal Concepts • Consideration of alternative disposal concepts • In-tunnel Axial Concept – more suitable for larger containers as no rotation of container • RWMD has identified practical options for emplacement of MPC type containers (e.g. NUMO (Japan) cavern system) • Suited to MPC package • Potential for earlier emplacement due to delayed buffer backfill

  15. Next Steps • NIA working group to consider scope of further research • Engagement with Government where implications for Managing Radioactive Waste Safely process • Operators to engage with local communities on site specific waste proposals for new nuclear power stations

  16. www.niauk.org

More Related