EWB-MAP Water Tank Project Construction Progress

EWB-MAP Water Tank Project Construction Progress. June 5-12, 2012. Map of Las Delicias Water System. DOWNHILL. Map of current Las Delicias Water System from ADESCO with approx house locations indicated. 260 Homes Served by Tanque 3. 291 Homes Served by Tanque 1. 33 Homes

summer
Télécharger la présentation

EWB-MAP Water Tank Project Construction Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EWB-MAP Water Tank ProjectConstruction Progress June 5-12, 2012

  2. Map of Las Delicias WaterSystem DOWNHILL

  3. Map of current Las Delicias Water System from ADESCO with approx house locations indicated 260 Homes Served by Tanque 3 291 Homes Served by Tanque 1 33 Homes Served by Tanque 2 DOWNHILL

  4. Proposed Water Distribution System 280 Homes Served by New Tank 117 Homes Served by Tanque 3 33 Homes Served by Tanque 2 154 Homes Served by Tanque 1 DOWNHILL

  5. Map of Current Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity DOWNHILL New 17,000 gallon tank Exisiting 11,000 gallon tank

  6. Proposed update to Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity Tank Construction Pipe connections Pipeline Plans Distribution of Work A F NEW DISTRIBUTION LINE 2a NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b E DOWNHILL NEW DISTRIBUTION LINE 2c B NEW TANK C

  7. DAY 1 – June 5, 2012

  8. Photos

  9. Day 2 – Wednesday June 6, 9 AM

  10. Day 2 – 3 PM

  11. Day 2 – 3 PM Miguel Martinez (Supervisor) Miguel Delgado (driver/handyman) from FIAT) Daniel Rivera (Engineer from Rotary) Holman (driver from FIAT) Sergio (LD ADESCO member) Mario (LD resident)

  12. Day 3 – Thursday June 7, 9 AM

  13. Day 4 – Friday June 10, 11 AM

  14. Day 5 – Saturday June 9, noon

  15. Day 6 – June 11: noon

  16. Day 7 – June 12 noon

  17. Day 7 – 4 PM – ‘mesita’ complete

  18. Schedule for Completion of Tank • Wed June 13: start laying rocks/sand for base of foundation • Thur June 14: continue laying rocks/sand for base of foundation • Fri June 15 – Tue June 19: cut/tie rebar and prepare form for foundation • Wed June 20: pour foundation • Rain could delay these tasks

  19. Photos

  20. Ordered tubing and fittings from local supply store in San Salvador

  21. Proposed update to Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity Tank Construction Pipe connections Pipeline Plans Distribution of Work A F NEW DISTRIBUTION LINE 2a NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b E DOWNHILL NEW DISTRIBUTION LINE 2c B NEW TANK C

  22. Proposed update to Water System (section relevant for EWB-MAP modifications)RED lines – supply lines to tank (uphill by pump)BLUE lines – distributions lines by gravity A F NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b E DOWNHILL NEW DISTRIBUTION LINE 2c B NEW TANK C

  23. Photos along Pipeline PathArea of Connection to Tubo Madre A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  24. Photos along Pipeline Path(location of valve box?) A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  25. Photos along Pipeline Path(location of valve box?) A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  26. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  27. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  28. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  29. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  30. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  31. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  32. Photos along Pipeline Path A NEW SUPPLY LINE 1 D NEW DISTRIBUTION LINE 2b B NEW TANK C

  33. Meeting with Mayor to discuss installation of pipeline • Alcalde (Mayor) Ingeniero Romeo Jose Barillas (alcaldiaopico@yahoo.com, 2331-3001) • Travelled to Alcaldia (Mayor’s office) with Alfredo Torres (member of LD ADESCO) on Tuesday June 12, 2012) • Got on waiting list at 8:30 & met with Mayor at 10:45 • Requested help digging trench and installing PVC tubing. Alfredo had official letter from ADESCO • Mayor knew about project (had been contacted by Ana Maria de Keene – honorary consul of El Salvador in Philadelphia) and agreed to help with everything including supplying the 4” (supply) and 2” (distribution) pipes. • Questions from mayor: • Is 160 PSI PVC acceptable? • Do you want cemented PVC or rapid connection? • Will send an engineer to evaluate poject. • Other questions (from RAC) • Location of valve boxes, air bleeds, T’s, cleanouts • Should prepare detailed plan to send to mayor ASAP

  34. Distribution of Work • EWB-MAP • Overall project management and communication between parties • Updating design verifying that work meets design specs. • Long term planning • FIAT (Sister Gloria) • Purchase of last minute supplies, order trucks of materials, submission of receipts to Rotary for reimbursement. Storage of supplies. • Organizing volunteers, hiring one mason • Las Delicias ADESCO • Organizing community labor (each house volunteers 1 day or pays $6 for another person to do the work) • Ensuring secure storage of supplies • Communication with Alcaldia • Daniel Rivera (Rotary San Salvador) • Purchase of supplies (1 week notice): rebar, concrete • Payment of supervisor and mason (hire one mason) • Local project management and oversight of supervisor (Miguel Martinez) • Alcaldia San Juan Opico • Installation of two lines (4” supply and 2” distribution) of tubing in the same trench between Calle Principal and Tanks.

  35. Project Expenses (Thru June 11)

  36. Contacts • FIAT guest house: 2-226-7610 • Miguel Delgado (FIAT driver/helper) cell: 7-570-8675 • Rene (LD President): 7-458-4150 • Miguel Martinez (Supervisor on work site): 7-465-0654 • Alcalde (Mayor) Ingeniero Romeo Jose Barillas (alcaldiaopico@yahoo.com, 2-331-3001)