Operator Training Simulator for co-generation plant Delesto 2. Arnhem 3-feb. 2010 Henk Assink. Chemical site Delfzijl. Delesto bv. 50/50 Joint Venture between AkzoNobel Energy and Essent Energy
E N D
Operator Training Simulator for co-generation plant Delesto 2 Arnhem 3-feb. 2010 Henk Assink
Delesto bv • 50/50 Joint Venture between AkzoNobel Energy and Essent Energy • Supplier of power, heat and utilities to 14 chemical plants on the site Delfzijl in the Netherlands • One of the largest co-generation plants in Europe(530 MW,750 t/h LP/IP steam) • 76 employees, operated by Akzo Nobel
Delesto 2 Delesto 1 IP steam LP steam
Delesto 2 • 9FA single shaf co-generation unit • Power output 350 MW • Extraction flow: 0-300 tons/hr • Partial upgrade to FA+e technology during HGPI 2002 • Base load unit, load flexibility within premix steady state (approximately 100 MW) • Honeywell TDC-3000 control system
Maintenance schedule Delesto 2 • Start commercial operation July 1999 • Combustion Inspection September 2000 (8k) • Hot Gas Path Inspection April 2002 (12k) • Combustion Inspection March 2004 (16k) • Major Inspection April 2006 (16k/32k) • Combustion Inspection May 2006 (16k) • Hot Gas Path Inspection April 2010 (12k)
AM 24 HM 12 (red) NIM 20/21 NIM 22/23 UCN 3 UCN 4 Overview Delesto 1 system DC PHD Level 3,5 FIBER OPTIC Fault Tolerant Ethernet ESVT Klok EST 2 EST 1 EST 26 EST 27 EST 3 AM 13/14 TPS File server LCN FIBER OPTIC HPM 05 HPM 05 HPM 07 HPM 07 HPM 09 HPM 13 HPM 13 HPM 09 HPM 11 HPM 15 HPM 11 HPM 15 HPM 17
AM 47 NIM 43/44 NIM 41/42 Overview Delesto 2 system DELESTO 1 Fault Tolerant Ethernet FIBER OPTIC EST 4 AM 45/46 LCN DELESTO 1 FIBER OPTIC Remote I/O HPM 05 HPM 05 FIBER OPTICS UCN 6 UCN 5 Remote I/O HPM 07 HPM 07 HPM 09 HPM 09 HPM 11 HPM 11 HPM 13 SMM 17 Safety Manager
Why an operator training simulator (OTS) • Because of high reliability the operator is not familiar to abnormal situations (other side of success) • Fully automated startup and shutdown sequences (two times push the button) • One unit start/shutdown per year with a five shift organizations this means one start/shutdown per five years • New operators do not have feeling with unit • Dynamic simulator
starting-point OTS • Operator interface look and feel • Modular system • Part of real DCS system • Part of LCM (Life Cycle Management) contract • Maintainable date-base • Dynamic simulation • Different scenarios by instructor • Use engineering system hardware • Time manipulation possible
AM HM Overview engineering / OTS system Instructor Facility DC Fault Tolerant Ethernet EST 1 EST 2 EST 26 EST 27 SX 3 ESVT TPS File server Plant Model TPS Emulation LCN NIM NIM HPM HPM UCN UCN SMM Safety Manager
UniSim Plant Simulator • Process Area Models • Cooling Water Systems • Gas Turbine & Auxiliaries • Condensate Boiler Feed Water • Steam Turbine & Auxiliaries • Generator & Auxiliaries • Control / Logic Model • GE Speedtronic MK 5 Governor
DCS Emulation • Plant Control / Logic • Start-Up & Shutdown Sequences • Triconex Protection System • Produced from actual plant configuration: • EB & AM files • AM / HPM CL files • Configuration files ( .NCF ) • Custom Data Point / Segment Definition files • Parameter files ( .SP )
LCN – Simulation Interface SX003 • Virtual Plant Control (VPC) for TPS Interface( SX003 ) provides interface between: • LCN and DCS Emulation / Plant Simulator • Instructor Station and DCS Emulation / Plant Simulator • Operates as an active node on the LCN • mimics the presence of NM41, NM43 & AM45
Operator & Instructor Stations • Operator Station ( EST ) • with same set of graphics as actual plant • Instructor Station • Graphical interface to access the facilities of the system( Running / Controlling the simulation & training ) • Student Monitoring • Field Operator Duty / Role Playing • Scenario Generation / Management
AM HM Fault Tolerant Ethernet NIM NIM HPM HPM UCN UCN SMM Demo Delesto OTS System • Booth #50