1 / 9

PIPE CRAWLER FOR THE REMOVAL OF RADIOACTIVE PLUGS

PIPE CRAWLER FOR THE REMOVAL OF RADIOACTIVE PLUGS. Team 14 Lee Brady ∙ Jose Matos ∙ Brian Posse Advisor Dr. Sabri Tosunoglu Project Feasibility Presentation January 14, 2010. Problem Statement.

Télécharger la présentation

PIPE CRAWLER FOR THE REMOVAL OF RADIOACTIVE PLUGS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIPE CRAWLER FOR THE REMOVAL OF RADIOACTIVE PLUGS Team 14 Lee Brady ∙ Jose Matos ∙ Brian Posse Advisor Dr. Sabri Tosunoglu Project Feasibility Presentation January 14, 2010

  2. Problem Statement • A Pneumatic Crawler will remove clogs that delay the U.S. Department of Energy operations as they transfer millions of gallons of highly radioactive sludge and slurry from leaking single-shell tanks to more secure double-shell tanks at national sites.

  3. Design Metrics • Crawler and components must: • Fit in a pipe having inner diameter of 3”. • Negotiate through 90˚ bends w/ turning radius of 4.25”. • Be able to pull its own weight including weight of tether. • Be radiation hardened. • Be capable of removing clogs that exist in pipelines.

  4. Conceptual Designs

  5. Evaluation of Prototype • Functionality • Proper programming of time intervals on inflation/deflation cycles and the mitigation of any leaks of pressurized fluid will be controlled in this stage. • Force • Record the maximum pulling force that can achieved by adjusting the pressure and vacuum settings in each air cavity.

  6. Evaluation of Prototype • Agility • The unit will be tested for its ability to complete a designed test-bed consisting of straight sections and elbows. • Speed • This test will provide the estimated time that will take for the unit to reach a plug. • Unplugging Capability • The effectiveness of the abrasive tool attachments to unplug simulant plugs will be studied.

  7. Prototype Controls and Functions • Pneumatic Controls • Compressed Air • Vacuum Lines • 3 S0lenoid Valves • PICKit • Hydraulic Controls • Electric Pressure Washer • Abrasive Tool Plug

  8. Conclusion • Construct a pneumatic crawler for the removal of radioactive clogs w/ removal tool powered by hydraulics • Prototype Testing • Study of pneumatic sequencing and pressures/vacuums • Effectiveness of unclogging tools

  9. Questions ?

More Related