1 / 55

There are (3) major Refineries in Iraq:

REFINING. There are (3) major Refineries in Iraq: 1- Doura Refinery – built in the Fifties of the last Century with a capacity of (70) kb1/d which was increased to (110) k b1/d by adding 4 (10) k b1/d units. 2- Basrah Refinery - built in the seventies of the last Century with a

tara
Télécharger la présentation

There are (3) major Refineries in Iraq:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. REFINING There are (3) major Refineries in Iraq: 1- Doura Refinery – built in the Fifties of the last Century with a capacity of (70) kb1/d which was increased to (110) k b1/d by adding 4 (10) k b1/d units. 2- Basrah Refinery - built in the seventies of the last Century with a capacity of (140) kb1/d which was increased to (180) k b1/d by adding 4 (10) k b1/d units. 3- Baiji Refinery- built in the seventies and eighties of the last Century with a capacity of (290) kb1/d which was increased to (310) k b1/d by adding 2 (10) k b1/d units.

  2. REFINING All these refineries .were simple designed to produce white products not exceeding (50 -55%) of the feed crude. Only Baiji has a hydrocracker units of (30)kb1/d capacity. All three refineries have lube oil plants of various capacities. These refineries sustained severe damage during the 1991 gulf war . They were all fixed and put int operation within 2 -3 months from the end of the said war , but were not restored to a healthy state . The long period of UN sanction inflicted more damage due to disrepair&lack of maintenance .

  3. REFINING Period April 2003 – Dec 2008 The operation of refineries was adversely affected by the security situation. Insurgent & terrorist attacks targeted crude oil & product pipe lines. Refineries suffered frequent stoppage of operation, either due to lack of crude oil or inability to evacuate products. This applies to the period 2005 – 2007 . In 2008 there is a definite improvement in the operation thus the daily average for refining has been gradually increasing coupled with decrease of oil products imports.

  4. Status End 2010 1- MIDLAND REFINERIES A- Doura Refinery Installed Capacity : 210kb 1/d. - 2 new CDUs,each of 70 kb1/d - both in operation. - A third Hydrotreater Reformer Unit 10 kb1/d – procurement phase. - Isomerisation Unit 10 kb1/d – Civil work & supply of equipment phase. - A power generation station 50 mw – under construction. - One New Boiler 150 ton/h with Demin Water Unit –completed & in operation. Second New boiler 150 ton/h under construction. - An RFCC Unit 40 kb1/d – FEED Package awarded. - New Cooling Tower – Contract awarded.

  5. Lube Oil Plants A- Doura Refinery There are 3 Lube Oil plant : - No:1 – completed 1959 by Foster wheeler - capacity 25 kton/y present operation at 85% of capacity . - No:2 – completed 1969 by Snam Projetee – capacity 36 kton/y present operation at 77% of capacity - No:3 – completed 1978 by Nigata – capacity 60 kton/y- present operation at 94% of capacity

  6. Future Plans A- Doura Refinery - Replacement of 3 CDUs 70 kb1/d total capacity with one CDU unit 70 kb1/d. - Additional treatment of Industrial water including circulation of treated water. - Improvement of Flare system to reduce emmissions. - Complete renovation of lube oil plants. - Replacement of old reformer units with new ones. - New Gas Oil hydrotreater units

  7. Status End 2010 MIDLAND REFINERIES B- Najaf Refinery: - 3 Distillation Units , (10)kb1/d each – in operation. - A Naphtha Hydrotreater & Reformer unit with all related utilities in the engineering phase. - Asphalt unit – planned.

  8. Status End 2010 MIDLAND REFINERIES C- Samawa Refinery - 3 Distillation Units , (10)kb1/d each – in operation. - A Naphtha Hydrotreater & Reformer unit with all related utilities in the engineering phase. - Asphalt unit – planned

  9. Status End 2010 1- MIDLAND REFINERIES D- Diwanya Refinery - One Distillation Unit , (10)kb1/d in operation. - 2rd Distillation Unit , (10)kb1/d under fabrication.

  10. Status End 2010 2- NORTH REFINERIES A- Baiji Refinery Complex – Capacity 310 kb1/d. - New Isomeration Unit – 19.6 kb1/d – Final stages of construction. - 6 New boilers – 400 ton/hr total capacity -under construction. - New power generation plants (85)mw – contracted. - New LPG unit for North Refinery , 400 tons/d – Award of contract under processing. - Upgrading of Waste Water Treatment System – under implementation. - Re-construction of (51) storage tanks – 9 Nos complete, 80% completion of remaining tanks. - Rehabilitation & De- bottle necking of Hydro- Cracker Unit – under evaluation with Designer & Supplier . - New FCC unit 50 kb1/d – Feasibility Completed

  11. Status End 2010 2- NORTH REFINERIES A-Baiji Refinery Complex - Lube Oil Plant , 250 kton/y – at present one train 125 kton/y is in operation. Second train is under rehabilitation. B- Kirkuk Refinery - 3 CDU 10kb1/d each – in operation. C- Kasak Refinery - one 10 kb1/d unit – in operation. - Second 10 kb1/d unit - civil work construction. - Waste Water Treatment Unit – under construction. - New Storage Tanks – under construction.

  12. Status End 2010 2- NORTH REFINERIES D- Qayarah Refinery - 4 Old Asphalt Units, one 180 cum /d & three 360 cum/d each - only one unit 360 cum/d is in operation at 50% capacity. other units are under rehabilitation . - A new Asphalt Unit is planned . - One 10kb1/d CDU operating on Kirkuk Crude - installed. - 2rd 10kb1/d CDU operating on Kirkuk Crude - under installation. - 8 storage tanks –under construction. E- Seeniyah Refinery - Three 10 kb1/d units – in operation - 10 storage tanks – under construction. - Waste Water Treatment unit – under construction.

  13. Status End 2010 2- NORTH REFINERIES F- Haditha Refinery - 2 units , 16 kb1/d total capacity – in operation. - 12 storage tanks – under construction. - Waste Water Treatment Unit – planned . Future Plans - Rehabilitation of Gas Oil Hydrotreating Units. - Rehabilitation & upgrading of lube plant. - Replacement of old reformer units.

  14. Status End 2010 3- SOUTH REFINERIES A- Basrah Refinery - New (70) kb1/d Distillation Units with an LPG unit (300) ton/d- under construction. - Third Hydrotreater Platformer Unit 10kb1/d -under construction. - New LPG unit (200) ton for Train(1) – procurement phase - New Isomeriation Unit (11) kb1/d - Delivery of equipment & Site preparation. - 3 New Boilers , 100 ton/h each – under installation. - New Waste Water Treatment Plant – Awarded. - New cooling Tower – under construction . - New FCC Unit 30 kb1/d – FEED package preparation phase. - Replacement of old reformer units.

  15. Future Plans - New Utility Package . - New Gas oil Hydrotreatment Unit- Design completed. - New Naphtha hyrotreater unit 15 kb1/d. - Upgrading of Instrumentation & Control. - Improvement of Flare System to reduce emmissions. - Up grading of waste water system & recirculation of treated water.

  16. Status End 2010 3- SOUTH REFINERIES B – Nasiriyah Refinery - 3 Distillation Units , (10)Kb1/d each in operation. - A Hydrotreater Reformer unit with all related utilities- Engineering phase. - A Waste Water Treatment unit – Evaluation of offers. - An Ro unit 50m3/h completed & in operation. - Expansion of utilities & tankage – planned. C- Missan Refinery - 3 CDUs , 10 kb1/d each – installed & in operation

  17. Refining Levels - year : 2004 404 k b1/d - = : 2005 377 = - = : 2006 356 = - = : 2007 329 = - = : 2008 443 = - = : 2009 447 = - = : 2010 523 = (Jan- Oct)

  18. Import of Oil Products Yearton/d Total Value 2004 3658.6 1731.2 million $ 2005 7706.3 4517.2 = = 2006 2302.7 3517.9 = = 2007 2402.5 1749.8 = = 2008 2603.4 2345.6 = = 2009 2016.0 1272.4 = = 2010 1472.0 1077.0 = = End of Aug * Import for Ministry of Electricity is not included

  19. Consumption of white Products Cubic Meters Legend Gasoline Gas Oil Kerosene

  20. NEW REFINERIES 1- Karbala Refinery Capacity 140 000 BPSD

  21. SITE INFORMATION: • Kerbala Refinery is located about (110) KM South west Of Baghdad. • Area : 4 X 3 Km2 • Coordinate U.T.M. : • N : 3580000 • E : 415000

  22. Products Specification will be according to EURO-4 as minimum required. • Gasoline , Kerosene &Gas oil with (10 ppm ) Sulphur content .

  23. Expected Product Quantities :

  24. 2-Maissan Refinery Capacity 150 000 BPSD

  25. SITE INFORMATION: • Maissan Refinery is located about (400) KM South Of Baghdad. • Area :( 2 X 3) Km2 • Coordinate U.T.M. : • N : 3537000 • E : 730000

  26. Products Specification will be according to EURO-4 as minimum required. • Gasoline , Kerosene &Gas oil with (10 ppm ) Sulphur content .

  27. Expected Product Quantities :

  28. 3- Al-Nassiriya Refinery Capacity 300 000 BPSD

  29. SITE INFORMATION: • Al-Nassiriya Refinery is located about (400) KM South Of Baghdad. • Refinery Area  5.6 Km2 • Coordinates U.T.M. : • N : 3413750 • E : 622900

  30. Products Specification will be according to EURO-4 as minimum required. • Gasoline , Kerosene &Gas oil with (10 ppm ) Sulphur content .

  31. Expected Product Quantities :

  32. 4-Kirkuk Refinery Capacity 150 000 BPSD

  33. SITE INFORMATION: • Kirkuk Refinery is located about (300) KM North Of Baghdad. • Area :( 2 X 3) Km2 • Coordinate U.T.M. : • N : 3937794 • E : 431192

  34. Products Specification will be according to EURO-4 as minimum required. • Gasoline , Kerosene &Gas oil with (10 ppm ) Sulphur content .

  35. Expected Product Quantities :

  36. Gas Processing - Rehabilitation of the second train in Khor al Zubair – South gas – under way. - Rehabilitation of Sour gas treatment units at NGL North Rumailah – under way . -Studies for New slug catchers at khor al Zubair & NGL & Sulphur recovery unit at North Rumailah – under way.

  37. Future Plans - Third Train in North Gas – Studies & Evaluation. - Expansion of existing compressor stations for Rumailah,Zubair&West Qurna Fields to match future production levels from these fields. - Expansion of NGL capacity of South Gas from present 1050 mmscf/d to 2500 mmscf/d. - Implementing Sour Gas treatment & Sulphur recovery Units at Khor al Zubair. - Building Power generation at Khor al Zubair. - Rehabilitation of LPG & Ng Export Terminal at Khor al Zubair.

  38. Present Installed Refining Capacity 1- Salah al Din Complex – Baiji – 310 mb1/d 2- Doura Refinery – Baghdad – 210 mb1/d 3- Basrah Refinery – Basrah -140 mb1/d + 70mb1/d under construction 4- - 6 small refineries , 30mb1/d – 180 mb1/d Kirkuk,Syniah-Baiji , Najaf,Samawa,Nasiriyah,Maisan - 1 small refinery at Diwaniyah – 20 mb1/d - 1 = = = Kasak –Neinewah – 10 mb1/d - 1 = = = Haditha – Anbar – 16 mb1/d Total- 886 mb1/d +70 mba under construction

  39. Operating Capacity The average operating capacity is in the 580 – 620 mb1/d. The short fall in refining capacity is due to - Shortage in delivery of crude oil - Frequent stoppages due to operational problems - Accumulation of fuel oil or Naphtha in small refineries.

  40. Main Projects in Existing Refineries - 3 Ismerisation Units at Baiji , Doura & Basrah – under construction. -2 Gasoline Reformers at Doura & Basrah- Procurement & Construction Phases. - Fcc unit at Basrah –FEED phase. - Fcc unit at Doura–FEED phase. - Fcc unit at Baiji – Feasibility Completed. -2Gas Oil Desulphurisation Units at Basrah & Doura- Bidding Stage . -3 small Gasoline Reformer units at Najaf ,Samawa& Nasiriyah- Engineering phase. - Power Generation Units at Doura & Baiji – under construction

  41. Nassiryah Refinery Process UnitsDesign Capacity & Licensors

More Related