1 / 13

ASD Procurements

ASD Procurements. Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009. Outline. Overview of Procurement Process Review Significant Procurements in Process Current Status Contract Award Status (Baseline vs. Current) Next Milestone Delivery Schedule

tawanag
Télécharger la présentation

ASD Procurements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009

  2. Outline Overview of Procurement Process Review Significant Procurements in Process Current Status Contract Award Status (Baseline vs. Current) Next Milestone Delivery Schedule Challenges Delivery, Storage & Assembly Upcoming Procurements Conclusion

  3. Overview of Sig. Procurement Process

  4. Storage Ring Magnets • Current Status • Quads & Correctors – Contracts issued • Sextupoles – DOE Approved • Large Aperture – In negotiation with vendor • Dipoles – Technical review (10/19) • Contracts spread to spread risk; can shift • Next Milestone – Issue all contracts; Track vendor progress • BL Contract Award Date – Aug/Sept, 2009 • Current Contract Award Date – Oct/Nov, 2009 • Delivery Schedule – On schedule for mid-2011 • Challenges – Complexity, Resources, • First major ASD procurement • Will produce Lessons Learned

  5. Storage Ring Girders • Current Status • SOW signed • Finalizing & checking drawings • Next Milestone – RFQ/RFP, Send out for bid • BL Contract Award Date – Oct, 2009 • Current Contract Award Date – Jan, 2010 (deliberate to avoid girder storage onsite) • Delivery Schedule – Compressed, but still end-2010 • Challenges – Alignment analysis, Verifying with lattice, • RFQ vs. RFP

  6. Linac • Current Status • SOW & Spec signed • RFP in BSA review • Next Milestone – Send out for bid • BL Contract Award Date – Jan, 2010 • Current Contract Award Date – Feb, 2010 • Delivery Schedule – Beg-2012 (commissioned by vendor) • Challenges - Resources

  7. Booster • Current Status • Specification & SOW in final review, awaiting feedback • Drawings & Appendixes being completed • Next Milestone – Sign off Spec & SOW, RFP creation • BL Contract Award Date – March, 2010 • Current Contract Award Date – March, 2010 • Delivery Schedule – Beg-2013 (commissioned by vendor), Compressed, On Critical Path • Challenges – PPM consumed with magnet • procurement, Semi-turnkey added • complexity

  8. Vacuum Chamber Extrusions • Current Status • Multipole – Contract issued • Dipole – Out for bid • Next Milestone – Award Dipole contract • BL Contract Award Date – Aug, 2009 • Current Contract Award Date – Oct, 2009 • Delivery Schedule – Compressed, On schedule for end-2009 thru mid-2010 • Challenges – Limited interest from vendors, Changed multipole profile, Vendor ability to hold tolerances, Long prototype phase

  9. Damping Wigglers • Current Status • Spec & SOW in process • Addressing vendor exceptions • Another national lab is potential vendor • Next Milestone – Sign Spec & SOW • BL Contract Award Date – Sep, 2009 • Current Contract Award Date – Feb, 2010 • Delivery Schedule – Late, mid-2011 instead of beg-2011, Delivery date dependant on vendor selection • Challenges – Feasibility of specifications, Limited vendors

  10. Other Procurements • Ultrasonic Cleaning Facility – Out for bid • Vacuum System Bimetallic Flanges – Contract issued • Environmental Enclosure – Out for bid • Hall Probe Bench – Contract issued • Moving Wire Bench – Spec in process • Precision Current Transducer – Contract issued

  11. Delivery, Storage & Assembly • Dedicated Receiving Area • Plan Started to Link Area Needed to Delivery Schedule • Storage locations being identified • Locations identified & secured for assembly of: • Magnets • Process Water System • Front Ends • RF • Electrical Systems • Diagnostics & Instrumentation

  12. Some Upcoming Procurements

  13. Conclusion • Much progress made, but some procurements are late due to resource and technical reasons • Booster is most pressing • PPM seems overloaded, but the load should lighten • Ways to makeup for delays being identified • Systems, procedures & templates in place • Delivery, storage & assembly plan in progress • Future procurements should go quicker due to experience

More Related