An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kinetic Energy Harvesting Weekly Meeting 6 October 23rd, 2013

  2. Last Time • PDR • Amherst bike shop visit • Cap self discharge test • 2.6V to 1.8V (800mV) in 60 hours • No longer a concern • Cornell Cup • Wild Card Option • Intel Atom processor October 22, 2013

  3. Motor Generator • Arrived finally • 2500 RPM = 12.8 V (open circuit) • Lower than quoted • 2500 RPM = 12.0 V (220 ohm load) • Better than expected • Lower RPM and better diodes? • 1.9A short circuit at 2500RPM October 22, 2013

  4. Concerns • TA: Generator back EMF • Force to turn shaft multiplies by gear ratio • Motor power vs force optimization problem • Bike gear prototype may not be useful • Only needed to determine optimal gear ratio • Can be achieved with RPM meter and drill • $14 on Amazon • Better off building one configuration only October 22, 2013

  5. RPM Meter • http://www.amazon.com/professional-tachometer-Non-contact-revolutions-Measurement/dp/B00DGLU1YK/ref=sr_1_2?ie=UTF8&qid=1382482344&sr=8-2&keywords=rpm+meter • 2.5 RPM to 100KRPM range • No contact needed • Reflective strip on generator • Accurate to 0.05% • Can help determine ratio before moving forward October 22, 2013

  6. Tasks • ECE webpage creation • Presentation in 2 weeks • Benchside meetings coming (4-5pm Thurs) • describe individual MDR deliverables • progress to date • general project idea • Peer review summary • Discuss new prototyping ideas October 22, 2013