SlideServe
Menu
Préférences
© SlideServe · v2026

Other Flight Pressure Systems

terra avatar
17 diapositives · 350 Views · Jul 17, 2014

Other Flight Pressure Systems. Phase III Flight Safety Review 12 Jan 2009. Flight Pressure Systems. In addition to the magnet cryosystem , AMS-02 has four additional flight pressure systems Transition Radiation Detector (TRD) Gas Supply Warm Helium Gas Supply Thermal Control System

Other Flight Pressure Systems - slide 1
01 / 17Other Flight Pressure Systems
1 / 17

Télécharger la présentation

Other Flight Pressure Systems
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Other Flight Pressure Systems Phase III Flight Safety Review 12 Jan 2009

  2. Flight Pressure Systems • In addition to the magnet cryosystem, AMS-02 has four additional flight pressure systems • Transition Radiation Detector (TRD) Gas Supply • Warm Helium Gas Supply • Thermal Control System • Tracker Thermal Control System (TTCS) • TRD Gas Supply and Warm Helium Supply include Composite Overwrapped Pressure Vessels (COPVs).

  3. TRD Gas Supply • Transition Radiation Detector uses a mixture of Xenon and carbon dioxide gas to identify incoming particles. • System is divided into three major regions • Box S: The primary gas supply, contains all the high-pressure elements. • Box C: The circulation box, contains the pumps used to circulate gas through the detector. • TRD: Within the detector itself, gas flows at low pressure through a series of small composite tubes and then back into Box C.

  4. TRD Box S

  5. TRD Box C

  6. TRD Straw Tubes

  7. TRD Gas Tanks • Xenon and CO2 is stored in two COPVs in Box S. • Both tanks were manufactured by Arde’ and are duplicates of previous designs. • Xenon tank was previously used on ISS Plasma Contactor Unit (PCU) • CO2 tank was previously used on X-33.

  8. Warm Helium Gas Supply • Valves used on the flight cryosystem are gas-actuated. • Parallel pipework system used to deliver helium for valve operation.

  9. Warm Helium Tank • Warm Helium Tank is a COPV manufactured by Arde’. • Tank is identical to previous design used on Pegasus vehicle. • Tank was designed for MDP of 5800 psi in Pegasus application, but AMS-02 will only pressurize to 2900 psi.

  10. Thermal Control System • Thermal Control System uses heat pipes and loop heat pipes to transfer heat to the main and zenith radiators. • Main radiators use ammonia as working fluid. • Zenith radiators use propylene as working fluid. • All pipes operate in sealed mode and have no nominal or fault venting. • Most tubes are embedded inside radiators, but a few run along the USS, the Vacuum Case, or the Cryomagnet Avionics Box (CAB). • All tubes are manufactured by Iberespacio and are standard designs used throughout space industry.

  11. Main Radiator Heat Pipe Layouts Ram RadiatorWake Radiator

  12. Zenith Radiator Loop Heat Pipes

  13. Tracker Thermal Control System • Tracker Thermal Control System is a two-phase carbon dioxide system used to remove heat from the Silicon Tracker. • Tubes run along the sides of the tracker, across the Vacuum Case upper flange, to condensers on the Tracker Radiators. • Small heat pipe used in accumulator to optimize operations. • System operates in sealed mode and has no nominal or fault venting.

  14. Composite Overwrapped Pressure Vessels • At Phase II Ground Safety Review, AMS-02 was asked to implement additional safety verifications based on draft COPV requirements. • Submitted Damage Control Plan for review. • All tanks reinspected by WSTF personnel. • Stress reports re-evaluated by ES4. • ES4 performed additional stress rupture calculations. • All AMS-02 COPVs passed inspection and stress report review did not identify additional issues. • All tanks and protective coverings are installed. • Stress rupture reanalysis ongoing.

  15. TRD Gas Supply Installed Configuration

  16. Warm Helium Tank Installed Configuration

  17. Conclusion • Details of each of these pressure systems are included in the Safety Data Package • TRD discussed in section 5.5. • Warm Helium Tank discussed in section 5.1.3. • Thermal Control System discussed in section 5.13. • Tracker Thermal Control System discussed in section 5.9.4. • Main pressure systems analysis included in Hazard Reports #4 and #5. • Flammability issues reviewed in Hazard Report #10.