1 / 7

Penetrations for Corrector Cables, Update After the 2007 Installation

This note initiates the planning for the installation of short straight corrector cables in the Booster enclosure after the 2007 installation. It includes information on cable designations and locations in various racks.

timmyj
Télécharger la présentation

Penetrations for Corrector Cables, Update After the 2007 Installation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Penetrations for Corrector Cables, Update After the 2007 Installation December 3, 2007 C. Drennan During the 2007 Booster Shutdown one half of the new correctors were installed. These were installed into the odd numbered long straight sections. All of the long straight corrector cables were pulled from the racks to the desired locations in the Booster enclosure. This note starts the planning for the short straight Booster corrector Cable runs.

  2. From G04-RR0 Issues: No issues. Penetration L5-8 is available to pull the SS cables. From Rack G04-RR0 Location: West Booster Tower Penetration Designations: Long Straight Cables, 2007 => L5-7 Short Straight Cables, 2008 => L5-8

  3. From G24-RR1 Issues: We would like to run the SS Cables through P-18. What signals are on these small cables in this penetration now? From Rack G24-RR1 Location: West Gallery, Period 24 Penetration Designations: Long Straight Cables, 2007 => BP24-P-17 Short Straight Cables, 2008 => BP24-P-18

  4. From G21-RR4 Issues: P-14 has a number of cables in it already. We need to identify these. From Rack G21-RR4 Location: West Gallery, Period 21 Penetration Designations: Long Straight Cables, 2007 => BP21-P-11 Short Straight Cables, 2008 => BP21-P-14

  5. From G16-RR2 Penetration Designations: Long Straight Cables, 2007 => BP16-P-09 Short Straight Cables, 2008 => BP16-P-08 From Rack G16-RR2 Location: East Gallery, Period 16

  6. From G14-RR5 From Rack G14-RR5 Location: East Gallery, Period 14 Penetration Designations: Long Straight Cables, 2007 => BP14-P-14 Short Straight Cables, 2008 => BP14-P-13

  7. From G11-RR7 Issue: Can we use BP11-P-2 =OR= BP11-P-9 for the Short Straight Cables? From Rack G11-RR7 Location: East Gallery, Period 11 Penetration Designations: Long Straight Cables, 2007 => BP12-P-05 Short Straight Cables, 2008 => BP11-P-02

More Related