80 likes | 203 Vues
This document outlines the recent updates and discussions regarding the ME1/1A commissioning process led by G. Rakness from UCLA. Key topics include the importance of retaining ME1/1A in the muon trigger, gas mixture adjustments in the CSC, and ongoing work on the CANbus projects. The document highlights local runs, firmware updates, calibration efforts, and upcoming commissioning meetings. It emphasizes the need for continued collaboration and problem-solving as the team prepares for beam operations in late October. Important tasks and goals are set for achieving a seamless commissioning process.
E N D
ME1/1A—revisited… Recall request from Wesley Smith regarding ME1/1A • “We cannot remove ME1/1 at high eta from the trigger since we need every single muon trigger for startup… Please do not remove any of the sections of ME1/1 from the trigger.” Snippet from TMB documentation: Couldn’t we just set CC[3]=0 (for TMB firmware types C and D) to enable ME1/1A in the trigger (like it used to be)? Do we want to do this? G. Rakness (UCLA)
Stuff at point 5 • We have taken many local runs with detector in various states, for example… • 9 – 23 February has ME4/1 OFF while they paint the forward shielding • csc-daq03 was revived • Updated to software version 6.9, including… • monitoring package update to TMB counters (ME1/1A version) • new TMB configuration parameters… • tmb_firmware_compile_type • alct_readout_without_trig • clct_readout_without_trig • match_readout_without_trig • mpc_block_me1a • I have been pushing people to work on CSC CANbus by example • I now know more about CANbus than I ever thought possible… • … I’m surprised our CANbus worked as well as it did… G. Rakness (UCLA)
Gas mixture change in CSC Recall: cost of CF4 in 2008 = CHF 400k… • CF4 reduces chamber aging in a high rate environment • Should not be necessary for commissioning with cosmic rays • Changed today at noon • 40% Ar + 50% CO2 + 10% CF4 40% Ar + 5% CF4 + 55% CO2 • How did we verify that the gas mixture was OK before we did this? • Measured mixture composition with gas chromatograph • Took local run, looked at gas gain plots in CSCValidation • Performed HV scan (see next page…) G. Rakness (UCLA)
HV scan from Tuesday… https://cmsdaq.cern.ch/elog/CSC/7703 This trace is identical to January 2008 and December 2007… Gas mixture is the same G. Rakness (UCLA)
To do at point 5 • Thursday: • Continue to push CANbus studies • Calibration run • Friday: • HV scan • local data run for gas gain • Next week: cooling work will make it not possible to power on both endcaps at the same time… In the meantime… • Track finder mezzanine card test + firmware updates • Update to online software version 6.10 • Uses configuration database G. Rakness (UCLA)
Beginning of shifts • From Chamonix meeting: slip in LHC schedule by ~6 weeks Beam likely in late October… Immediate question (to be discussed at tomorrow’s commissioning meeting) is: when do we start CSC shifts? • CMS commissioning note: there are biweekly mid-week global runs beginning first week of March What would we (UCLA) like to do? • My point of view: since the power-up procedure has been fixed, it is no longer painful to turn off/on every day. I believe the major pain will be extracting volunteers to run for the mid-week global runs… G. Rakness (UCLA)
Other stuff • Iterated with Alex M about including ALCT test firmware… he doesn’t think it will be a problem to include it in a beam version of ALCT firmware, but would like to see us test it out at 904 and point 5 first… G. Rakness (UCLA)
To do • Get TMB + ALCT test firmware working • at 904 • At point 5 on chambers with problems • Push CANbus studies at point 5 • Come up with numbers for • (CSC latency + cable lengths) and • (RPC latency + cable lengths) so that I can decide if I believe the RPC folks about their latency… • Combine firmware version check into configuration check moving towards a single push-button check of all configuration… G. Rakness (UCLA)