1 / 8

QRL Leak Tests the story so far……….

QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133). QRL Leak Tests in LS1. TE-VSC baseline objectives for QRL in LS1:  Collaborate with TE-CRG to repair known internal leak in S4-5,

urbana
Télécharger la présentation

QRL Leak Tests the story so far……….

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) Paul Cruikshank TE/VSC - QRL Leak Tests - LS Committee, 24/5/2013

  2. QRL Leak Tests in LS1 TE-VSC baseline objectives for QRL in LS1:  Collaborate with TE-CRG to repair known internal leak in S4-5,  Helium to insulation vacuum - leak test all sectors,  Air to insulation vacuum - leak test all sectors,  Reconfigure safety valves (ECR),  Maintain fixed pumping equipment,  Add additional pumping at subsector extremities (ECR),  Execute all tasks in shadow of SMACC planning. Paul Cruikshank TE/VSC - QRL Leak Tests - LS Committee, 24/5/2013

  3. QRL Sector 4-5 header C tightness (recall) Problem appeared during Xmas break 2010/2011 (transient operation on LHC cryogenics). Deformation of QRICA corrugations were caused probably by thermal contraction of the compensator with condensed air blocked between the corrugations. air leak during operation → ice at compensator → fast desorption at warm-up > 40 K → expansion of header piping with ice present → damage to compensator → helium leak Additional pumps were added by TE/VSC to continue operation in 2011, 2012 & 2013 up to LS1. The aim of LS1 intervention is to replace the faulty compensator (no magnet removal) Courtesy K. Brodzinski Source: S. Claudet, N.Veillet & AL

  4. QRL Leak Tests – Observations May ‘13 6 of 8 QRL sectors measured, 5 new internal leaks confirmed: failure scenario appears same as S4-5; 2 existing internal leaks – S4-5, ssB, line C at Xmas 2010 – LS1 planned repair, S7-8, ssA, line B at installation – no evolution, no action. Paul Cruikshank TE/VSC - QRL Leak Tests - LS Committee, 24/5/2013

  5. QRL Leak Tests – to do immediately Measure helium residuals in remaining 2 sectors – S1-2 & S5-6*. For each internal leak: Confirm which header is leaking*, Longitudinally localise the helium leak under vacuum*, X-ray the suspect compensators (& others?), Check for air leaks on the vacuum vessel, Collate data & open NCRs. Repair scenario(s) cannot be judged until above info is available. *Several issues to overcome: cryo-lockout – 1% helium in headers, SMACC & magnet exchanges – headers cannot be pressurised, VSC instrumentation off at P7– need mobile equipment, Co-activities in S5-6, S6-7 – SMACC, Paul Cruikshank TE/VSC - QRL Leak Tests - LS Committee, 24/5/2013

  6. QRL Leaks – Proposed action plan Agree the immediate actions with TE-CRG, EN-MME TE-MSC, others?? Integrate the new activities within master planning, Execute the first repair as soon as possible to get feedback, Identify mitigation measures that could be implemented during LS1 to protect the QRL during future operation/warm-up. Report regularly to LSC on status. Others……? Paul Cruikshank TE/VSC - QRL Leak Tests - LS Committee, 24/5/2013

  7. QRL Leak Tests Back-up slide Paul Cruikshank TE/VSC - QRL Leak Tests - LS Committee, 24/5/2013

  8. Helium leak in QRL S45 subsector B- insulation vac evolution 23 December 2010 Pirani gauge readings Pressure rise of 4 mbar in < 30 s Suspect rapid desorption of air leak ~ 12 months of air leak at 1 E-2 mbar.l/s (280000 mbar.l of gas) Cannot be attributed to cryosorbed helium (only ~ 100 mbar.l possible for this cryostat) 4 mbar Subsector B B-C A-B Subsector C Subsector A E-3 mbar 17:56 17:58 Prepared by P. Cruikshank LMC P. Cruikshank

More Related