1 / 25

Interaction Region Vacuum Chamber Upgrades

Interaction Region Vacuum Chamber Upgrades. Presented by: Scott DeBarger Contributors: D. Arnett, B. Bigornia, C. Carr, J. Langton, S. Metcalfe, D. Kharahk, M. Kosovsky, N. Kurita, R. Pope, N. Reeck, A. Sheng, B. Smith. Outline. Forward Q2 Chamber Q1/Q2 HOM Bellows

Télécharger la présentation

Interaction Region Vacuum Chamber Upgrades

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Interaction RegionVacuum Chamber Upgrades Presented by: Scott DeBarger Contributors: D. Arnett, B. Bigornia, C. Carr,J. Langton, S. Metcalfe, D. Kharahk, M. Kosovsky,N. Kurita, R. Pope, N. Reeck, A. Sheng, B. Smith

  2. Outline • Forward Q2 Chamber • Q1/Q2 HOM Bellows • HER Q4 & Q5 Vacuum Chambers; HOM Absorbing Bellows • LER Q4 R Temporary Chamber • LER Q4 & Q5 Vacuum Chambers • DS-7 Transition • LER 2062 Chamber • LER 2143 Collimator • Interaction Region HOM Absorbers • Additional Diagnostics • HOM Straight Bellows Interaction Region Vacuum Chamber Upgrades p.2 of 25

  3. Forward Q2 Chamber • Replaced Q2R with a Q2L chamber in 2002 • Improve Beam Stay-Clear and reduce HOM generation (see mask at right) • Chamber failed (following operation) due to material flaw in the GlidCop • Original Q2R chamber reinstalled in 2003 • Does not maintain Beam Stay-Clear • No evidence that it creates increased HOMs • New Q2R installed March 2006 • Opportunistic installation in conjunction with Q1/Q2 bellows seal • Still no effect on HOM generation observed Interaction Region Vacuum Chamber Upgrades p.3 of 25

  4. Q1/Q2 HOM Bellows • Identified as a critical upgrade at previous review • Technically very challenging • Limited space available • Anticipated high power loads • Design compromises travel during installation to accommodate new HOM absorption arrangement • 61 mm maximum tile/slot length • Absorbing tiles are open to the convolutions • No additional tile set needed in bellows cavity • HER Arc Bellows features • Spring, Stub, RF shield • (See M. Sullivan talk) Interaction Region Vacuum Chamber Upgrades p.4 of 25

  5. Q1/Q2 HOM Bellows • RF Seals replaced 22 February 2006(see M. Sullivan talk) Installed design • Materials in hand (AlN-SiC tiles, GlidCop, bellows) • Working aggressively to complete new bellows modules • Hope to install during current shutdown New stub in fabrication Interaction Region Vacuum Chamber Upgrades p.5 of 25

  6. HER Q4 & Q5 Chambers • HER Q5 & Q4 Chambers • General issues • Mechanical & HOM failures in the NEG screens • Beam Stay-Clear (BSC) & Luminosity cone restrictions • Thermal motion of magnets • Original Q4 & Q5 are rigid chambers that have minimal to no clearance to their respective magnets • Global alignment errors between the 10-meter Collimator and Q5 L and between Q5 R and High Power Dump. • History of mask and flange failures due to SR heating • NEG heating during high current operation Interaction Region Vacuum Chamber Upgrades p.6 of 25

  7. HER Q4 & Q5 Chambers • Design goals (achieved) • LER: 4.5A, HER 2.2 A operation • Respect the defined BSC/Luminosity cone and existing magnet envelopes. • Maintained a 2mm gap to poles and a 3mm gap to coils • Reduce operating thermal gradients • Improve kinematics and stabilize BPMs • Added a bellows between Q4, Q5 • Added a flex flange between Q2L & Q4L • Replaced beampipe supports • Decrease the RF leakage to the pumps • Screen hole diameter reduced to 3 mm and depth increased to 6mm Q5 NEG RF Screen Interaction Region Vacuum Chamber Upgrades p.7 of 25

  8. HER Q4 & Q5 Chambers • HER Q5 L Chamber • Installed Fall 2005 • HER Q4 & Q5 R and HER Q4 L Chambers • Installed beginning in August 2006 • Installation revealed vertical misalignment of ~9 mm at HER High Power Dump (corrected) • Aluminum clamshell design • Profile matched to available space • Excellent assembly distortion control • Straightness in y-z (vertical) plane = +/- .030” • Straightness in x-z (horizontal) plane = +/- .011” • End to end roll = 9 mRad Q5 L installation Interaction Region Vacuum Chamber Upgrades p.8 of 25

  9. Performance of Q5 L Chamber • HER Q5 L • Installed Fall 2005 • Beam induced heating of NEG dramatically reduced Temperature of Q5 L NEG (Mar 05-Aug 06) HER Current (Mar 05-Aug 06) Interaction Region Vacuum Chamber Upgrades p.9 of 25

  10. Q4/Q5 Bellows with Absorber • Mechanically decouples Q4 & Q5 vacuum chambers • Absorbing tiles above and below beam orbit Absorbing Tile Q4 side, 10” flange Inconel Spring Finger GlidCop Stub GlidCop RF Shield Finger Welded Bellows Cooling – not shown Q5 side 12” flange Interaction Region Vacuum Chamber Upgrades p.10 of 25

  11. LER Q4 Right Temporary Chamber • LER Q4 R chamber replaced by a straight drift tube on22 February 2006 • Concern that the chamber outgassing and/or sparking caused beam aborts (found to be not true). Interaction Region Vacuum Chamber Upgrades p.11 of 25

  12. LER Q4 & Q5 Chambers “Flex Flange” detail • Two major issues addressed in redesign • Beam induced NEG heating(leading to NEG outgassing) • Thermal motion of the Q2,4,5 raft/magnets • New design for LER Q4 & Q5 • Improved RF screens • Added “Flex Flange” at chamber inboard ends • Improved mask cooling; also additional cooling added Old Screen New Screen Interaction Region Vacuum Chamber Upgrades p.12 of 25

  13. LER Q4 & Q5 Chambers • Status • Chamber fabrication and assembly complete • Q4 vacuum processing complete; Q5 chambers are on bake • Ready to begin installation of Q4 when project engineer returns on 26 October “Flex Flange”prior to final assembly Interaction Region Vacuum Chamber Upgrades p.13 of 25

  14. LER Q4 & Q5 Chambers • Status • Chamber fabrication and assembly complete. • Q4 vacuum processing complete; Q5 chambers are on bake. • Ready to begin installation of Q4 when project engineer returns on 26 October Interaction Region Vacuum Chamber Upgrades p.14 of 25

  15. DS-7 Octagonal-to-Round Transition • Chamber absorbs a large amount of LER SR originating near the IP(1.2 kW @ 4.5 A, 3.1 GeV) • Previous DS-7 chamber not well cooled • New chamber incorporates GlidCop body and improved cooling • Installed Nov 2005 Interaction Region Vacuum Chamber Upgrades p.15 of 25

  16. LER 2062 Chamber • Vacuum leak developed on 10 Dec 2005 - sealed temporarily. • LER 2062 chamber replaced1 May 2006 • Buttons in nearby chambers fell on 2 & 5 May, prompting effort to remove LER Collimator • Repaired chamber reinstalled on 16 May 2006 2062 chamber Interaction Region Vacuum Chamber Upgrades p.16 of 25

  17. LER 2143 Collimator • LER 2143 Collimator removed 16 May 2006 • Intended to control backgrounds in BaBar • HOM generator affecting downstream LER • Damage to the collimating surface being evaluated Interaction Region Vacuum Chamber Upgrades p.17 of 25

  18. Interaction Region HOM Absorbers • High current running prompts a desire to manage HOM heating in the LER • Two HOM absorbing chambers to be added to the LER (3044 & 1153) • RF Shield 3.5 mm slots in 2.5 mm thick GlidCop • Absorption (calculated by S. Novokhatski, S. Weathersby): • Monopole – 0.0027% • Dipole – 54% • Other Dipole – 88% • Quadrupole – 89% • Design selected for high absorption over a broad frequency range • All absorption curves relatively flat – no major spikes or troughs Uses Ceralloy 13740Y (Aln-SiC) tiles Matches existing LER Octagonal cross section Install November 2006 Interaction Region Vacuum Chamber Upgrades p.18 of 25

  19. Interaction Region HOM Absorber (1153) Elliptical VAT Valve (reinstalled) Elliptical to Octagon Transition Octagonal Bellows Octagonal to LER Arc Transition (New) e+ Octagonal to Elliptical Mask (New) HOM Absorber Improved masking at 1153 location Interaction Region Vacuum Chamber Upgrades p.19 of 25

  20. Additional Diagnostics • Vacuum gauges added • 9 additional hot filament gauges distributed through the Interaction Region • These gauges are less sensitive to non-vacuum beam effects Interaction Region Vacuum Chamber Upgrades p.20 of 25

  21. Additional Diagnostics • Fast(er) data sampling • SLAC standard history buffers store at 6 minute intervals • Data Archiver stores specified channels at 1 second intervals Interaction Region Vacuum Chamber Upgrades p.21 of 25

  22. Additional Diagnostics • (Really Fast) Abort Logger • Multiple channels sampled @1kHz for 10 seconds surrounding a beam abort • To date, only in place in IR-2; all other IRs added this downtime • Digital Video Recorder, Rotating Mirror, … Interaction Region Vacuum Chamber Upgrades p.22 of 25

  23. HOM Straight Bellows • Goal – to create a HOM absorber in a defined modular space • HOM absorber will damp and absorb the power, preventing neighboring components from absorbing excessive HOM power • Design optimized with MAFIA simulations • Installed one unit on 1 May 2006 • Three additional units deployed in Oct 2006 Interaction Region Vacuum Chamber Upgrades p.23 of 25

  24. HOM Straight Bellows • Measurements confirm that the straight bellows-absorber in Region damped 40% of the available HOM power • Very good agreement with calculated performance of a 7cm length absorber Modes that leak past the RF shield finger still see the absorber Interaction Region Vacuum Chamber Upgrades p.24 of 25

  25. Summary • The Interaction Region Vacuum System is receiving a major reworking in 2006 • Principal efforts are centered around high current running • Management of synchrotron radiation and higher order mode heating has been addressed • Diagnostic capabilities have been developed and implemented to improve our abilities to understand future problems should they arise • We feel that the Interaction Region vacuum system will be ready to meet the demands of planned PEP-II operations Interaction Region Vacuum Chamber Upgrades p.25 of 25

More Related