OVER-THE-RHINE. PLAYGROUND SCHEDULED TO BE COMPLETE OCTOBER 2011. BANDSTAND SCHEDULED TO BE COMPLETE OCTOBER 2011. BANDSTAND SCHEDULED TO BE COMPLETE OCTOBER 2011. WASHINGTON PARK FALL EVENT PROGRAMMING. 3CDC Weekly Events:
E N D
WASHINGTON PARK FALL EVENT PROGRAMMING • 3CDC Weekly Events: • Wednesdays 6-8 p.m. (Civic Lawn): Cincinnati Sports Kickball League , Sept. 5 ‐ Oct. 15 [9 weeks] • Thursdays 6-8 p.m. (Civic Lawn): Cincinnati Sports Kickball League Sept. 5 ‐ Oct. 15 [9 weeks] • Fridays 12-1 p.m. (Bandstand): SCPA in the Park, Sept. 14 ‐ Sept. 26 [6 weeks] • Saturdays 2‐4 p.m. (South End) Kids Fall Fest, Oct. 6 ‐ Oct. 27 [4 weeks] • Saturdays 7‐11 p.m. (Civic Lawn): Family Fright Nights , Oct. 6 ‐ Oct. 27 [4 weeks]
WASHINGTON PARK Partners
RESIDENTIAL SALES Gateway I,II,III & IV: 183 of the 186 condos (97%) are sold
RESIDENTIAL LEASING Gateway I,II,III & IV: 68 of the 68 apartments (100%) are leased
COMMERCIAL LEASING 85% of 91,000 SF commercial space leased.
COMMERCIAL LEASING THE ANCHOR, 1401 RACE STREET
COMMERCIAL LEASING CORE: A MOVEMENT STUDIO, 1423 VINE STREET
COMMERCIAL LEASING • Coming Soon: • Hapa, 1335 Vine Street • Kaze, 1400 Vine Street • Currently negotiating multiple letters of intent; would bring total leased SF to 85% of available space.
COMMERCIAL LEASING Saengerhalle Office Building, home of 3CDC
SAENGERHALLE Projected Employees Saengerhalle Tenants SF Business Type 3CDC 7,485 Developer 26 Northpointe 1,650 Developer 6 Necco 6,520 Foster Parenting 15 SampleSaint 3,300 Mobile Media 15 Kurt Platte 1,650 Architect 8 Vitrue Social Media and Branding 3,100 12 Four Entertainment Group 2,510 Entertainment 8 1,194 Law Firm 10 KMK 2,100 --- --- Office Space - Available Restaurant Space - Available 2,730 --- --- Total 32,265 100
COMMERCIAL LEASING Parvis, 1400 Block of Vine
3CDC OTR DEVELOPMENT Future/ Land Bank Complete/ Under Construction Mercer Commons/ Gateway V
MERCER COMMONS • Phase I • 3,900 SF Commercial/Office • 28 Condos • 340-space Parking Garage • CDF committed $2.56 million of state and federal NMTC • Phase II • 67 Apartments (30 affordable) • 10,600 SF commercial space • OHFA awarded project low income housing tax credits and also received historic tax credits from State of Ohio • Phase III • 59 Apartments • 3,100 SF commercial space
PAINT BUILDING • Renovation of 1400-1404 Vine • Project Cost: $4.1 million • 3,680 SF restaurant space • 6,000 SF office space
3CDC OTR DEVELOPMENT Land Banked/ Future Projects Complete/ Under Construction Mercer Commons/ OTR Phase V
3CDC OTR DEVELOPMENT Land Banked/ Future Projects Complete/ Under Construction