PCC/TEPPC Project Coordination and Path Rating Task Force Report

PCC/TEPPC Project Coordination and Path Rating Task Force Report. TEPPC Meeting, June 16-17, 2010 John Cupparo. Recap. The WECC Board approved the revised PCC Overview of Policies and Procedures for Project Coordination Review, Project Rating Review, and Progress Reports (PCC Document).

wayne
Télécharger la présentation

PCC/TEPPC Project Coordination and Path Rating Task Force Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PCC/TEPPC Project Coordination and Path Rating Task Force Report TEPPC Meeting, June 16-17, 2010 John Cupparo

  2. Recap • The WECC Board approved the revised PCC Overview of Policies and Procedures for Project Coordination Review, Project Rating Review, and Progress Reports (PCC Document). • Assignments continue

  3. Assignments • Continue to consider possible structural changes to the PCC Document on roles and responsibilities of PCC and TEPPC with respect to Project Coordination and Regional Planning. • Synergies and new responsibilities • Structural Change – 1 document, 2 documents or 3 document? • Review, clarify and streamline the Procedures for Project Rating Review within the PCC Document. The Goal is a clear process that has no duplications and will delineate between PCC and TEPPC responsibilities.

  4. Progress To Date • Two conference calls since approval of revised PCC procedure document • Issues: • Overlaps between the responsibilities of PCC and TEPPC • Both PCC and TEPPC investigate the transmission system in the 10-year planning horizon • Implications: “Transmission Plans” from TEPPC Process – vs. transmission project coordination by sponsors in PCC Process • Cost allocation • Timing • Need tie-back to regional policies, FERC Order 890 planning, DOE requirements • Transparency and open stakeholder requirements for planning • Need a process for the Region to come to consensus on regional “Transmission Plans” • Reliability performance from PCC needs to be input into RTEP process • Need a way to examine the guidelines to reflect the TEPPC planning process • Need to streamline, simplify, and untangle the Rating Process

  5. Two Tasks: • Review the TEPPC Planning Protocol and the PCC Procedures for Project Coordination Review (focusing on the 11 items on Project Coordination) • Overlaps? • Clarify work products and responsibilities. (Grace Anderson, Rich Bayless Scott Cauchois, John Cupparo, Bill Pascoe, Chifong Thomas, Scott Waples and Tim Wu) • Review the Phases 1, 2 and 3 (starting with Phase 1) in the PCC Document’s Procedures for Project Rating Review • Issues or difficulties with implementation • Objective is a clearer document with no duplications between PCC and TEPPC processes. (Kent Bolton, Tom Green, Kyle Kohne and Chifong Thomas) The Task Force welcomes comments

  6. Agreement: • The 11 items, as modified, will need to be completed and accepted by PCC regardless of whether a project chooses to satisfy the Project Coordination requirement through PCC or TEPPC • The WECC/TEPPC RTEP Process will produce “Transmission Plans” and Resource Scenarios as per the DOE agreement • Further discussions on the issues of overlaps in responsibilities of the two committees • Next face-to-face meeting: July 14, 2010

  7. Schedule • Jun 2010 – Progress Report • Aug 2010 – Draft White Paper to PCC • Sep 2010 – Finalize White Paper • Oct 2010/Mar 2011 – PCC Approval for Structural Changes • Dec 2010/Apr 2011 – WECC Board Approval

  8. Questions?