MQXF Short model and prototype plans

MQXF Short model and prototype plans. P. Ferracin, G. Ambrosio. HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN. Program overview Short model status and plans Long model plans “Links”. MQXF project schedule.

wbauer
Télécharger la présentation

MQXF Short model and prototype plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN

  2. Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”

  3. MQXF project schedule Paolo Ferracin, Giorgio Ambrosio • Short model program: 5 CERN-LARP models, 2014-2017 • Coil fabrication started in 03/2014 • First magnet test (MQXFS1) in 08/2015 (3 LARP coils, 1 CERN coil) • Long model program: 2 (CERN) + 3 (LARP) models, 2015-2018 • Coil fabrication starts in 2015: 02 (LARP), 10 (CERN) • First magnet test in 11/2016 (LARP) and 11/2017 (CERN) • Series production: 10 (CERN) + 10 (LARP) cold masses, 2018-2022 • Coil fabrication starts in 01/2018 • First magnet test in 10/2019

  4. Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”

  5. Short model program 2017 2014 2015 2016 CERN coil RRP coils, CERN 1st set RRP coils, CERN 2nd set PIT, CERN 1st set LARP coil RRP coils, LARP 1st set RRP coils, LARP 2nd set Mirror Models MQXFS1-2, 1st coil set MQXFS3-4, 2nd coil set MQXFS 5, PIT Paolo Ferracin, Giorgio Ambrosio • 3 models with first set of coils • All tested by LARP • Coil design update by March 2015 • Second set of coil start in Oct. 2015 • 2 models with 2nd set of coils • PIT coils and models in 2016-2017

  6. Short model statusCoil fabrication LARP coil #1 completed LARP coil #2 completed LARP coil #3 Prep. for impregn. at BNL LARP coil #4 Winding CERN coil #103 Winding CERN coil #001 (Cu) completed CERN coil #101 (Low-grade) Completed CERN coil #102 Prep. for impregn. Paolo Ferracin

  7. Short model statusModels Paolo Ferracin, Giorgio Ambrosio • 2 identical support structures fabricated • One at CERN, one shipped to LBNL • Same CAD model and same fabrication companies • 150 mm mock-up being tested • Mirror magnet to be tested in Feb.-Mar. 2015

  8. Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”

  9. LARP prototypes 2015 2016 2017 2018 RRP coils, 1st set RRP coils, 2nd set RRP coils, 3rd set Mirror MQXF1-1b MQXF2 MQXF3 Paolo Ferracin, Giorgio Ambrosio Winding in Feb. 2015 3 sets of coils 2 long prototypes before start of pre-series coil fabrication

  10. CERN prototypes 2017 2018 2015 2016 RRP coils PIT coils Mirror MQXF1-1b MQXF2 • Winding in Oct. 2015, reaction in mid 2016 • 1 set of RRP coils, 1 set of PIT coils • 1 long prototypes before start of pre-series RRP coil fabrication Paolo Ferracin, Giorgio Ambrosio

  11. Prototypes status Paolo Ferracin, Giorgio Ambrosio • LARP • taking the lead with 4 m coil fabrication starting in February 2015 • Equipment upgrades in progress: • Automatic (Selva) winder (FNAL) • Curing mold (FNAL) • Vertical test facility (BNL) • Coil tooling is under procurement • Structure assembly tooling under design • CERN • Coil and tooling CAD models in progress • Price inquiry in Jan./Feb. 2015

  12. Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”

  13. Links 2015 2016 2017 2018 Paolo Ferracin, Giorgio Ambrosio Short mirror  LARP long coil MQXFS1  CERN long coils MQXFS3  LARP long II set MQXFS4  LARP long III set MQXFS5  CERN long PIT 3 long models results ~before start series coils