Cook Slurry Explosive Site

Cook Slurry Explosive Site. Background. Property Owned By Utah “SITLA” since statehood Leased to Cook Associates Inc., “Cook” 1978-2008 Lease was terminated hostilely, subject to litigation (2003-2008) Cook manufactured ”ANFO” slurry. More Background. SITLA conducts a Phase I (Fall 2008)

yale
Télécharger la présentation

Cook Slurry Explosive Site

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cook Slurry Explosive Site

  2. Background • Property Owned By Utah “SITLA” since statehood • Leased to Cook Associates Inc., “Cook” 1978-2008 • Lease was terminated hostilely, subject to litigation (2003-2008) • Cook manufactured ”ANFO” slurry

  3. More Background • SITLA conducts a Phase I (Fall 2008) • SITLA requests Utah County Sheriff Department’s Bomb Squad to secure “portable explosives” (February 2009) • SITLA requests EPA assistance (April 2009) • Removal Site Inspection done April 13, 2009

  4. ANFO Slurry • Relatively Stable, High Explosive • Ammonium Nitrate (60-90%) • Fuel Oil (5-10%) • Sensitizers/Oxidizers (2-4%) • Spacer, e.g. Styrofoam (1-5%) • Emulsifier, e.g. animal fat (5-15%) • Used largely in Mining Industry

  5. April 2009 Site Visit • Explosives business non-operational, since at least 1998 • Large inventory of ANFO materials left on-site • Site relatively secured (moderate fence, locks) but deteriorating • Residential development encroaching, well within ½ mile presently

  6. May 2009 • After April site visit, EPA put its locks on the fence gate and provided site security • In May, EPA initiated inventory of chemicals and began cleanup • EPA accessed an explosives expert through the START contract

  7. Cleanup Complete • Cleanup complete by June 27, 2009 • EPA costs were approx. $400,000 • Cost recovery will follow • Potential “takings” claim