Backwards Compatibility L4 – L2

Backwards Compatibility L4 – L2. W. Weterings LBCC - 14. L4 PSB injection modification as currently planned. Removal L2 equipment ( and modify). Removal obsolete cabling. Installation L4 equipment. Installation L4 cabling. Minimum intervention time -> 3 Months.

yanka
Télécharger la présentation

Backwards Compatibility L4 – L2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Backwards Compatibility L4 – L2 W. Weterings LBCC - 14

  2. L4 PSB injection modificationas currently planned Removal L2 equipment (and modify). Removal obsolete cabling. Installation L4 equipment. Installation L4 cabling. Minimum intervention time -> 3 Months.

  3. Keeping Linac2 as a backup • by de-commissioning De-commission L2 equipment. (radioactive) Storage of L2 equipment. If possible leave L2 cabling in place. Removal obsolete cabling. Installation L4 equipment. Installation L4 cabling. Additional intervention time -> 2 Months. L4 to L2 Conversion time -> 5 Months.

  4. Keeping Linac2 as a backup • & leave L2 equipment in place (BA361) Additional installation space for L4 equipment. De-commission L2 equipment in tunnel. If possible leave L2 cabling in place. Removal obsolete cabling. Installation L4 equipment. Installation L4 cabling. Additional intervention time -> 1 Months. L4 to L2 Conversion time -> 4 Months.

  5. General Issues Space management, Integration (BA361). Campaign to remove already obsolete cabling, equipment in coming shutdown. Additional budget required for vacuum chambers (current plan is to modify existing pipes for L4). Investigate if KSW position for L4 is compatible with L2 operation.