1 / 22

Bill Bojorquez VP, System Planning August 16, 2007

Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop. Bill Bojorquez VP, System Planning August 16, 2007. North American Interconnected Grids. NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION (NERC). The ERCOT grid:

yosef
Télécharger la présentation

Bill Bojorquez VP, System Planning August 16, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Intermittent Resources and Demand Response Integration2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August 16, 2007

  2. North American Interconnected Grids NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION (NERC) • The ERCOT grid: • Covers 75% of Texas land • Serves 85% of Texas load • 38,000 miles of transmission lines • >550 generation units • Physical assets are owned by transmission providers and generators, including municipal utilities and cooperatives ERCOT connections to other grids are limited to direct current (DC) ties, which allow control over flow of electricity

  3. Current Wind Development • ~3,300MW installed capacity of wind generation in-service • ~2,000MW additional wind development with signed interconnection agreements • Steady build out has allowed for transmission, modeling and operation integration Additional bulk transmission lines will be required for > ~5000MW from West Texas • ~29,000 MW additional wind development in interconnection study process

  4. ERCOT Load • 62,339 MW summer peak demand • Majority of load is concentrated in eastern half of state • Dallas • Austin • Houston • San Antonio

  5. Effective Load Carrying Capability (ELCC) of Wind Process: • Run the ERCOT LOLP model with the base set of generating units and a generic thermal generator (550 MW) and determine the expected unserved energy. • Remove the generic thermal generator and add new wind generation with detailed profiles until the same expected unserved energy is achieved. • The amount of new wind generation will have the same effective load-carrying capability as the 550-MW generic thermal generator • Update study every two years Results: • 6,300 MW of wind had the same load carrying capacity as 550 MW of thermal generation (i.e., 8.7%).

  6. TX Senate Bill 20 (2005) • Increased renewable energy goal • 5,880 MW by 2015 • 10,000 MW by 2025 • Set up process for the PUC to designate Competitive Renewable Energy Zones (CREZs) • ERCOT contracted AWS Truewind to identify areas with best wind resource potential in Texas • AWS identified highest CF 100MW sites and clustered into 25 areas

  7. 12000 Potential Wind Resource 10600 9600 8300 • Nearly 100,000 MW above 35% capacity factor (CF) • Concentrated in western half of state 2700 4600 2200 6200 6000 2900 7900 6900 4700 Approximate west to east transfer capacity – 3,200MW 3000

  8. 12000 New Transmission Required 10600 9600 8300 2700 • Existing system from west Texas fully subscribed • Significant distances and costs associated with adding bulk transmission 4600 2200 200 miles 6200 6000 2900 7900 6900 4700 150 miles 3000

  9. ERCOT Study Results • ERCOT’s 2006 study identified new lines and upgrades to allow transfers from CREZ areas • Allowed for incremental 1,000 to 5,000 MW of wind capacity • In addition to 5,000 MW existing plus planned • Goal was to provide options from which the PUC could designate areas and amounts

  10. Draft CREZ PUCT Designations (Scenario 3) 3720 4 4560 1, 2 5215 9, 10 2051 19 2890 5, 6

  11. Challenges MW Midnight Noon • Level of wind penetration relative to the size of the interconnection • Minimum system load dispatch issues (~ 21,000 MW) • Ancillary Services to support large wind changes • Voltage and transient stability modeling and assessments • Completing system reviews for the CREZ designations over the next six months

  12. Next Steps • Stage 1 (August): Final order in Docket 33672 on CREZs and “rough” transmission requirements • Stage 2 (December/January): Completion of “CREZ Transmission Optimization Study” • Stage 3 (December/February): PUC to designate transmission constructors • Stage 4 (December ’08/February ’09): CCNs developed and submitted • Stage 5 (June ’09/August ’09): CCNs approved • Stage 6 (TBD): Completion

  13. Demand Response

  14. Reserve Margins 2000-2012 Percentage difference between projections for peak demand and available generation/resources Target for reliability: 12.5% Over 65,000 MW of new generation is in planning or under consideration, but not all will be built. 12.5%

  15. Interruptible Tariffs in the Regulated World • Prior to 2001, 3200 MW of customer load (mostly industrials) provided an emergency interruptible safety net • Customers’ year-round electric rates were discounted in exchange for this • In May 2000, ERCOT deployed interruptible loads four times during emergency conditions • Unseasonably hot weather • Generation outages • New wave of gas-fired generation had not yet come online • ERCOT began full retail competition on January 1, 2002

  16. Interruptible Load in the New (restructured) Market • Loads Acting as a Resource: • Market-based replacement for interruptible tariffs • 1,989 MW currently registered and qualified • ERCOT demand forecast is reduced by 1,112 MW of “high confidence” demand response • LaaRs can provide ERCOT Ancillary Services (operating reserves) & receive capacity payments regardless of whether they are actually deployed • LaaRs provide 50% of ERCOT Spinning Reserve requirement (1,150 MW of 2,300 MW total) • Market price: ~$13 per MW per hour • Price-responsive demand is significant in ERCOT – but not yet readily reported • Additional demand response is obtained on coincident peak periods due to Transmission Tariff incentive

  17. LaaR Participation Growth in LaaR registration in MW

  18. LaaR Deployments • LaaRs can be deployed in 4 ways: • Automatic trip based on Under Frequency Relay settings • Verbal dispatch by ERCOT during EECP event (deployed as block) • Verbal dispatch by ERCOT during frequency event reportable to NERC (deployed as block) • Verbal dispatch by ERCOT to solve a local congestion issue (location-specific) • LaaRs have been deployed four times in the past 16 months: • April 17, 2006 Emergency Electric Curtailment Plan (manual) • Oct. 3, 2006 frequency event (manual) • Dec. 22, 2006 frequency event (UFR & manual) • July 2, 2007 frequency event (manual)

  19. Emergency Interruptible Load Service (EILS) • Service provided by loads (customers) willing to interrupt during an electric grid emergency in exchange for a payment • Last resort prior to firm load shedding (rotating outages) • Deployed ONLY in the late stages of a grid emergency • Goal is 500 MW to 1,000 MW subscription • Minimum subscription not met for spring and summer 2007 • New RFP out for fall 2007 ‘Another tool for the operator toolbox’

  20. Deployment During Emergency Operations ERCOT Operators have flexibility to skip Step 3 if frequency is decaying rapidly. In these cases EILS would be deployed immediately after Step 4 to enable faster recovery.

  21. Consideration on Demand Response (DR) • Should DR be considered a firm resource? If so what types of DR • Does DR defer transmission investment? • ERCOT concluded it should not • Summer 2006 MISO experience showed DR may not be useful unless transmission additions are made • Does DR stifle development of newer, more efficient, and cleaner generation resources?

  22. Q&A ON OFF • Questions?

More Related