html5-img
1 / 19

WCCUSD Bond Program Construction Update

WCCUSD Bond Program Construction Update. Ohlone Elementary School Phase 1 – West Campus 02/11/14. Ohlone Elementary School Phase1 West Campus. Original Completion Date: July 21, 2013 Projected Completion Date: June 1, 2014 Percent Complete: 90%

yule
Télécharger la présentation

WCCUSD Bond Program Construction Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WCCUSD Bond ProgramConstruction Update Ohlone Elementary School Phase 1 – West Campus 02/11/14

  2. Ohlone Elementary SchoolPhase1 West Campus

  3. Original Completion Date: July 21, 2013 • Projected Completion Date:June 1, 2014 • Percent Complete:90% • Planned Move-in Date: June 1 to August 1 • Approved C/O’s to date: $1,471,876 = 8.4% Ohlone Elementary SchoolPhase1 West CampusGeneral Information

  4. Ohlone Elementary SchoolPhase1 West Campus South Planters

  5. Ohlone Elementary SchoolPhase1 West Campus Courtyard

  6. Ohlone Elementary SchoolPhase1 West Campus Typical Classroom

  7. Ohlone Elementary SchoolPhase1 West Campus Typical Classroom

  8. Ohlone Elementary SchoolPhase1 West Campus Typical Learning Wall

  9. Ohlone Elementary SchoolPhase1 West Campus Main Entry

  10. Ohlone Elementary SchoolPhase1 West Campus Play Area

  11. Ohlone Elementary SchoolInterim Housing Plan02/11/14

  12. Bid Advertisement: March 4, 2014 • Open Bids: April 8, 2014 • Notice of Award : April 16, 2014 (ratification) • Notice to Proceed: April 28, 2014 Ohlone Elementary SchoolInterim Housing PlanBidding Schedule

  13. Ohlone Elementary SchoolInterim Housing Plan Site Plan – Phase 2.1

  14. Ohlone Elementary SchoolInterim Housing Plan Site Plan – Phase 2.1

  15. Ohlone Elementary SchoolPhase 302/11/14

  16. Ohlone Elementary SchoolPhase 3 Landscape Plan

  17. Ohlone Elementary SchoolPhase 3 Site Plan

  18. Current Status: Drawing Revisions • Submit to DSA: March 2014 • Back Check: July 2014 • Bid Advertise: July 23, 2014 • Open Bids: August 26, 2014 • Notice of Award: September 10, 2014 • Notice to Proceed: September 25, 2014 Ohlone Elementary SchoolPhase 3General Information

  19. Ohlone Elementary SchoolPhase 3

More Related