SlideServe
Menu
Préférences
© SlideServe · v2026

El Cerrito High School Stadium Construction Update - July 15, 2014

marlo avatar
14 diapositives · 282 Views · Jul 28, 2014

This update details the ongoing construction progress of the El Cerrito High School Stadium, including site plans and work completed by general contractor Wright Contracting, chief architect WLC Architects, and construction manager Hector De Leon. The project, with a contract amount of $13,438,000, commenced on January 27, 2014, and is set for completion on September 27, 2015. Key activities include retaining wall construction, site grading, and underground utilities installation, with a change order totaling $10,285.

El Cerrito High School Stadium Construction Update - July 15, 2014 - slide 1
01 / 14El Cerrito High School Stadium Construction Update - July 15, 2014
1 / 17

Télécharger la présentation

El Cerrito High School Stadium Construction Update - July 15, 2014
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. WCCUSD Bond ProgramConstruction Update El Cerrito High School Stadium 07/15/2014

  2. El Cerrito High SchoolStadium Conceptual Design

  3. General Contractor Wright Contracting • Architect of Record WLC Architects • Construction Manager Hector De Leon • Project Engineer Maria Zupo • Inspector of Record Kris Gilbert El Cerrito High SchoolStadiumProject Team

  4. El Cerrito High SchoolStadium Site Plan

  5. Contract Amount $13,438,000 • Notice of Award 11/21/13 • Notice to Proceed 01/27/14 • Duration 608 days • Completion Date 09/27/15 • Change Order $10,285.00 (0.07%) El Cerrito High SchoolStadiumGeneral Information

  6. Site retaining walls at Ashbury and Colusa • Fence piers at Colusa • Building retaining walls and foundations • Site grading and compaction • Underground utilities El Cerrito High SchoolStadiumProgress Update

  7. Backfilling at Ashbury

  8. Site Walls and Foundation

  9. Building Footings

  10. Retaining Wall Construction at Colusa

  11. Retaining Wall Construction at Ashbury

  12. Retaining Wall Construction at Ashbury

  13. Tree Planting

  14. El Cerrito High SchoolStadium Ashbury Avenue Elevation