An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Full Depth Reclamation Current Practice Testing Variability Presented To: Canadian User Group for Asphalt Sunday, November 15, 2009 Delta Beausejour Hotel Moncton, New Brunswick Tom Dziedziejko AME Materials Engineering

  2. FDR • Rehabilitation Technique that processes the full depth of asphalt pavement and a predetermined portion of the underlying base materials • Uniformly pulverizes and blends to provide an upgraded and homogeneous material

  3. FDR Equipment • Pulverizing drum rotates in an up-cut direction or opposite to the forward direction of travel. • Including some underlying granular helps cool cutting tools and enhances pulverization action • Allows simultaneous injection of stabilizing agents.

  4. Pug-Mill and Expansion Manifold Screen Deck FDR Equipment Belt Scale Crusher • Paver Laid FDR • Recycling Trains • Pulverize, Wind row, Pick up

  5. Distresses That Can Be Treated • Cracking • Age, Fatigue, edge, slippage, block, longitudinal, reflection, continuity • Ride Quality • Bumps, Localized Depressions, Cross fall correction, • Permanent Deformation • Rutting, Shoving, Wash Boarding • General Deterioration • Raveling, Potholes, Stripping, Delamination, etc. • Inadequate Structural Capacity

  6. Candidates for FDR • Good Candidate • Good But Approach with Caution • Potential serious underlying problems • Enhancement likely required

  7. Candidates for FDR • If existing pavement structure is adequate for loads then simple pulverization and regrading may be all that is required before applying surface. • Corrective aggregate may be required to ensure adequate drainage and mechanical properties of the treated material. • If structural enhancement is required then stabilizing agents can be added • Type of agent used should be selected based on the properties of the material present.

  8. Types of Stabilizing Additives • Bituminous • Foamed Asphalt • Asphalt Emulsions • Chemical • Portland Cement • Lime • Fly Ash Types C and F • Kiln Dust (Lime/LKD or Cement/CKD), Cement, Lime Blends • Combinations of the above • Bituminous additives blended with Chemical additives

  9. Types of Stabilizing Additives • Popularity of Recycling is spawning interest in new stabilizers and additives • Foam Enhancing additives • Pine Tar Emulsions

  10. Bituminous Additives • Asphalt Emulsions • Coats all aggregates with emulsion • Emulsion breaks leaving particles cemented together with bitumen • Paving can not proceed until emulsion break is complete • Days? Weeks? Cement sometimes added to accelerate break of emulsion

  11. Bituminous Additives • Foamed Asphalt • Fast becoming the most popular choice for FDR • Small amount of water added to hot asphalt results in foam • Pulverized material needs fines present up to 20% • Foam mixes with fines present in material to form a mastic binder • Mastic spot welds to larger aggregate in material to form bonds that hold mix together • Aggregates with PI as high as 15 treated successfully with no special processes • Typical delay before paving - two days

  12. Additive Selection for FDR • FDR is a Soil Stabilization Technique • When Bituminous Additives are used the process becomes a Hybrid Asphalt and Soil product • Asphalt products provide a binder system • Produces a flexible material with properties that resist fatigue and adds flexibility to the processed mat. • Additives used provide some enhancement to asphalt interaction with soils but also impacts soil properties similar to soil stabilization techniques.

  13. Chemical Additives • Lime • Most often used where soil has high PI (>10) • Benefits • Mitigates effect of reactive clays • Reduces PI of soil after application and reduces swelling potential • Decreases susceptibility to moisture damage (stripping) • Increases tensile and compressive strength of mix • Typical addition 1% to 3%

  14. Chemical Additives • Portland Cement • Most often used where soil has low PI (<10) • Primarily adds strength to weak materials • Benefits • Increases compressive strength of mix. • Strength increase over time • Impact on moisture susceptibility variable (stripping) • Typical addition 1% to 2% • Excessive addition results in potential cracking of the stabilized soil

  15. Chemical Additives • Fly ash • Fly ash is a pozzolan typically requiring presence of lime or hydrating cement to gain strength • Some clays can react with calcium oxide in Type C Fly ash alone resulting in strength gain. • Some fly ash has percentage of lime present that allows some hydration • Potential to Mitigate effect of reactive clays - Lime • Slower strength gain than cement but carries on longer • Excessive addition results in potential cracking of stabilized soil Data Source: Job Report Cold Recycling WR 2500: Foam recycling in Estes National Park, Colorado /USA

  16. Pre Engineering • Rule of Thumb Engineering is the Most Costly Form of Design • Proper Engineering Assessment should be carried out to identify the best choice of additive. • Must consider : • Amount of strength enhancement required. • Pavement Structural Design – Traffic? • Type and quality of base materials present • Drainage Characteristics • Presence of Clays and Silts • Plasticity Index • Pavement Drainage • Ditching • Sub drains

  17. Pre Engineering • Thickness of existing pavement • Optimize percent of pulverized pavement in process depth • + 60% RAP • Identify excessively thick areas • Over 200mm pavement depth could be a problem to process due to equipment capacity • Consider Pre-milling Options to reuse excess in other parts of project. – Shoulder stabilization

  18. Pre Engineering • Proper Mixture Design • Pre tender laboratory design trials to confirm additive selected will work is advisable. • Mix design before construction is compulsory

  19. Internal = 34oC Surface = 28oC Internal = 26oC Surface = 24oC Testing Variability • Accurate Test Results Dictate Acceptance • Stabilized Sample Temperature is Critical Temp = 25 C: Strength = 360 Temp = 26 C: Strength = 340

  20. Test Variability • Strength Change with Varying Conditioning Temperature

  21. Testing Variability 2 Hrs Room Curing 24 Hrs Room Curing 4 Hrs Room Curing

  22. Testing Variability • Optimum Moisture – Field Sample – AC 2.8% • Strength Varies with moisture content at time of compaction

  23. Conclusions • Select FDR based on engineering design • Selected process and enhancement should be based on existing conditions. • Chemical treatments should be established using Material requirements • Ensure Quality Verification Testing is completed accurately • Sample Temperature significantly influences results