ECAL DCS status: Readout and cabling (outside ECAL)

ECAL DCS status: Readout and cabling (outside ECAL). S. Zelepoukine IHEP Protvino/ETHZ 17.06.2003. Outline. DCS readout options DCS cabling (outside ECAL) Conclusion. DCS readout options – layout. CMS. balcony. PC/PVSS – PTM, HM --------- PLC – TSS. ECAL. Readout electronics.

zarek
Télécharger la présentation

ECAL DCS status: Readout and cabling (outside ECAL)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ECAL DCS status:Readout and cabling (outside ECAL) S. Zelepoukine IHEP Protvino/ETHZ 17.06.2003 S. Zelepoukine

  2. Outline • DCS readout options • DCS cabling (outside ECAL) • Conclusion S. Zelepoukine

  3. DCS readout options – layout CMS balcony PC/PVSS – PTM, HM --------- PLC – TSS ECAL Readout electronics 100 m 5 m Readout electronics 50 m 120 m Counting room USC55 Cavern UXC55 No electronics inside CMS ! (all electronics is accessible – at least during CMS shutdowns) S. Zelepoukine

  4. DCS readout options -- subsystems • PTM – precision temperature monitoring: • Keithley 2750 (DMM + multiplexing): sensor excitation; raw signal measurement/conversion; data acquisition; GPIB/Ethernet interfacing to a PC-PVSS. • ELMB: sensor excitation (separate current source); raw signal measurement/conversion; data acquisition; CANbus remote connection to a PC-PVSS. • [MUX+RBFE] – development cancelled (no exact data for overall accuracy at the time of RBFE ordering – may 2003) • HM – Humidity monitoring: Commercial (or developed in-home) transmitter + Keithley / ELMB. • TSS – Temperature safety system: [MUX+RBFE] + PLC (ADC conversion, data processing, alarm interlocks). S. Zelepoukine

  5. DCS readout– PTM CMS balcony ECAL ELMB + Current src PC/PVSS 2 5 m GPIB or Ethernet 100 m CANbus 50 m Keithley 2750 1 120 m Cavern UXC55 raw signals Counting room USC55 Raw signal: DC, 10 uA (excitation)  ~1.4V at 18oC (100K thermistor)  ~140mV at 18oC ( 10K thermistor) S. Zelepoukine

  6. DCS readout– HM CMS balcony 100 m CANbus ECAL 2 PC/PVSS ELMB transmitter 50 m Keithley 2750 1 100 m 0-5V DC Cavern UXC55 raw signals Counting room USC55 Raw signal: AC, <1 mA / 0.3-1V / ~ 400 Hz (sensor excitation) Transmitter output: 0-5V DC S. Zelepoukine

  7. DCS readout– TSS CMS balcony PC/PVSS 100 m 0-5V DC ECAL Ethernet interlocks MUX+RBFE PLC 50 m Cavern UXC55 raw signals Counting room USC55 Raw signal: DC, 10/100 uA (excitation)  max 50mV (RBFE input) RBFE output: 0-5V DC S. Zelepoukine

  8. DCS cabling (outside ECAL) • Cable lengths: • SM/Dee – balconies in UXC55: 50m for EB (? – to be checked with CMS integration) 70m for EE (? – to be checked with CMS integration) • Balconies – counting room in USC55: 100 m (? – to be checked with CMS integration) • Radiation resistance – PE cables can safely be used. • Cable type – STP (shielded twisted pair); 0.09 – 0.13mm2 • Grounding – cable shield grounding point ?? S. Zelepoukine

  9. Conclusion • Urgent– define cabling and patch panel connectors for EE (installation early 2004). • PTM has different cabling (balcony – counting room) depending on electronics choice. solution: all sensor signal cables go to the balcony; then either analog cables (to keithley) or CANbus (to PC). • Readout electronics – will be tested in H4 in summer 2003. S. Zelepoukine