1 / 17

Gordon’s Corner Road Over US Route 9

Gordon’s Corner Road Over US Route 9. Mahesh Patel, P.E. George Afful, P.E. Gregory Bitsko, P.E. About the Bridge. Built in 1939 Two span concrete encased steel girder bridge with an open joint at the centerline of the deck creating four superstructure quadrants/sections.

zasha
Télécharger la présentation

Gordon’s Corner Road Over US Route 9

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gordon’s Corner RoadOver US Route 9 Mahesh Patel, P.E. George Afful, P.E. Gregory Bitsko, P.E.

  2. About the Bridge • Built in 1939 • Two span concrete encased steel girder bridge with an open joint at the centerline of the deck creating four superstructure quadrants/sections. • Vertical underclearances • 13’-9” southbound • 14’-0” northbound • Bridge exhibits numerous locations of impact damage with loss of encasement and damage to bottom flange of fascia stringers. • Numerous overhead utilities impact constructability. These lines cross immediately over the east and west abutments of the structure and cross Route 9 above the north fascia of the bridge.

  3. About the Bridge

  4. Proposed improvements • Replace the entire superstructure and deck to increase the underclearance to a minimum of 15’-0” • Electro-Chemical Chloride extraction for substructure preservation • Prefabricated superstructure units to reduce the construction duration • Self-Propelled Modular Transporters (SPMTs) to remove existing superstructure in sections and install replacement units without relocating utilities • Superstructure replacement will be completed in ONE weekend, beginning at 9PM Friday and ending 6AM Monday. No other significant traffic impacts anticipated.

  5. Self-Propelled Modular Transporters (SPMTs) • Heavy lift system traditionally used in the oil industry • A series of interconnected or linked modules, which are computer controlled to operate as a single lifting unit • Each module has its own power supply system and has an unrestricted range of movement on the ground • System can move forward, backward, sideways, diagonally, as well as in circular and carousel (spin) motions • Units adjust vertically between 10” and 16” depending on the manufacturer.

  6. Video presentationIsland Park BridgeOttawa, Ontario

  7. To start video, double click photo

  8. North Tennent Rd. Wickatunk Rd. US Route 9 Franklin Ln. Gordon’s Corner Rd. Franklin Ln. Tennent Rd. US Route 9

  9. Alternate Ramp Access North Tennent Rd. Wickatunk Rd. US Route 9 Franklin Ln. Gordon’s Corner Rd. Franklin Ln. Tennent Rd. Alternate Ramp Access Staging Area (Municipal Parking Lot) US Route 9 Southbound Demolition

  10. Alternate Ramp Access North Tennent Rd. Wickatunk Rd. US Route 9 Franklin Ln. Gordon’s Corner Rd. Franklin Ln. Tennent Rd. Alternate Ramp Access Staging Area Staging Area (Municipal Parking Lot) US Route 9 Southbound Installation

  11. Alternate Ramp Access North Tennent Rd. Wickatunk Rd. US Route 9 Franklin Ln. Gordon’s Corner Rd. Franklin Ln. Tennent Rd. Alternate Ramp Access Staging Area Staging Area (Municipal Parking Lot) US Route 9 Northbound Demolition

  12. Alternate Ramp Access North Tennent Rd. Wickatunk Rd. US Route 9 Franklin Ln. Gordon’s Corner Rd. Franklin Ln. Tennent Rd. Alternate Ramp Access Staging Area Staging Area (Municipal Parking Lot) US Route 9 Northbound Installation

  13. Advantages • Eliminates 8 to 12 months of utility relocations vs. crane installation. • Eliminates daytime lane restrictions for utility relocation. • Saves over $600,000 in estimated utility relocation costs. • Work will be completed in one weekend rather than 10 to 14 months.

  14. SPMT Considerations • Pick weights generally not a concern. • Allows multiple construction activities to occur concurrently • Construction activities no longer “linear”; reduces time. • SPMT’s can be costly. $375,000 for equipment on this project. • Staging area selection critical. Close to site and adequate area required. • Different suppliers use different techniques affecting staging requirements.

  15. SPMT Considerations • Check utilities in staging area. Still need lifting equipment. • SPMT costs requires very compressed construction schedule. Design and planning are critical. • SPMT use can’t be dictated. Use incentive/disincentive provisions with very compressed schedule to “encourage” use. Refer to FHWA website. • Provide detailed equipment specifications. Similar systems are not the same. Circular, carousel and crab movements are critical to defining SPMT. • Get the suppliers to visit the site!!!

  16. Project Design Considerations • Pier set as control for geometry - narrow width. • Existing headers removed to top of seats to eliminate conflicts. Prefabricated superstructure with replacement headers. • Removing headers provides greater width to accommodate construction adjustments. • Existing wingwalls removed to top of seats to eliminate conflicts. Partial demo required to replace bridge parapet, demo simply extended. • Steel bolster eliminates one round of grouting. • Disc bearings provides greater construction tolerances. • Innovative incentive/disincentive provision. Incentive period ends 6PM Sunday, disincentive begins 6AM Monday.

  17. Thank You!

More Related