1 / 14

Programme-level Multi-Year Funding Commitment

Version 3. Simplify MyPBAS related operations and Ensure Multi-Year Planning & Budgeting in Programmes toward FY14 Budgeting Process. Programme-level Multi-Year Funding Commitment. Blue: added in version 2 Green: added in version 3. Background.

zwi
Télécharger la présentation

Programme-level Multi-Year Funding Commitment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Version 3 Simplify MyPBAS related operations and Ensure Multi-Year Planning & Budgeting in Programmes toward FY14 Budgeting Process Programme-level Multi-Year Funding Commitment Blue: added in version 2 Green: added in version 3

  2. Background • When LEAP was introduced in 2005, Programme-Projects structure started. (previously it was Project-its components) • Methodologies of Programme/Project Planning/Designing and Management became well organized. • Programme/Project Financial System became complicated • Budget files, PBAS entries, C/F and Project Core and Logframe Financial Report became 5 times • But, Donor restriction (mainly SP) is not changed • If same Programme, it seems that many SOs have flexibility of fund allocation among Projects • WV’s Development Programme Approach (IPM adoption) requires more flexible operation to work with local partners Not changing Programme-Projects structure in Development theory and accountability-level, change to Programme-level Commitment as one figure

  3. Where we stand now • Jan 21/22: Conducted two discussion WeBEX inviting SO IPG heads, SO IPG Finance heads, SDOs, RFDs and RFMs. Feedback received from 8 SOs, 2 ROs and 10 NOs including Operation/Programme, Ministry Quality and Finance. • Feb 20: Discussed in GFFT call (GC Finance, RFDs, SO IPG Finance heads) inviting GFO and DPE/IM. Feedback received from 7 SOs and 2 ROs. The most of feedback required clarifications on the proposed new business process. • The direction to simplify MyPBAS operation with the related works was endorsed by SO&ROs/NOs, and especially NOs appreciate more flexibility so that they can accommodate field-level timely needs. • Attached feedback summary focus on key concerns/issues, cartelized by 5 areas, and add comments/clarification with the name of groups to follow up. Texts in blue are based on the feedback after GFFT call. • SO internal operation issue: SP economic model/PCPY based approach, SP Reserve management • Business protocol: Loosing SOs’ control power at project-level, too much flexibility • Programme financial management issue: why only for SOs, overspending risk, poor agreement status of PDD/MY Budget, NOs capacity for better budget management • Roll-out • Clarification: meaning of “commitment”, accounting, etc. • Based on the additional suggestions, this 3rd version is developed.

  4. Scope • The funds which have no specific donor restrictions on project allocation under the same Programme • Mainly Sponsorship • But not limited, e.g., PNS general funding which has no donor restrictions. • Grants (Gov’t, Multi, PNS) are out of scope • Funding commitment which is tied with the specific activities should be made in a separated MyPBAS document (individual T4 code) by SOs (no change) • E.g., FY14 ADP total budget of $500K is funded by Sponsorship mainly but a part of Education project is funded by PNS Grant with $50K. • SO enters $450K to SMP and $50K to Education project in MyPBAS.

  5. Pre-conditions & Directions • Pre-conditions • No design changes on IT systems such as • MyPBAS DB • SunSystem: v6 is now roll-out • Horizon: system linked with LEAP budget template • LEAP Budget Template: v10 is not yet fully implemented • Project Core & Logframe Financial Report Template: new template starts from FY13 Q2. • No structure change on Programme and Project • Directions • Simplify, Reduce not-value-added work • Keep project-level accountability • Ensure the concept of Multi-Year Planning & Budgeting in Programme • Give more flexibility of annual cashflow and budget reallocation among projects under the same programme, but no overspent in each year-end per programme. • Ensure responsibility of line management in NOs and ROs for programme quality assurance functions aligned with one Operation one Organization.

  6. Overview MY Budget Budget Framework Project Core & Logframe Financial Report MyPBAS SO enter one big $ NO enter five $ over lifecycle Annual Budget ITD Budget YTD Actual ITD Actual Revised CY Budget Living Budget Inception-to-date (ITD) Budget/Actual is cumulative budget/actual of the phase. If in 3rd year of the current phase, ITD budget/actual is total budget/actual from 1st year to 3rd year.

  7. Budget Types • Multi-Year Budget (MY Budget) • This is 3 to 5 years of lifecycle budget created along with Programme Design Document (PDD). • MY Budget is be kept over 3 to 5 years of lifecycle unless PDD is revised or material budget change such as caused by exchange rate, inflation, etc. • This will be used as Inception-To-Date (ITD) Budget. • Revised Current Year(CY) Budget • This is one-year (CY) updated budget along with revised one-year (CY) Detailed Implementation Plan (DIP) • Revised CY Budget reflect previous year’s accomplishments. For example, if there are some remaining activities but need to carry out, those activities are included in the Revised CY Budget. • It is called “Annual Budget” in Project Core & Logframe Report. • Both use LEAP Budget Template (currently v10.1)

  8. Key Business Process (1)

  9. Key Business Process (2)

  10. Example - MyPBAS 440(70+370) is the cap for NO for Year 2 total budget for Project A & B

  11. 3-Year in MyPBAS

  12. PCFR and NO CF Explanation Forms CY SS Actual MY Budget (= Cumulative amount of PBAS fresh commitments) Revised CY Budget

  13. Transition Plan • Projects that have SO Forecasts at Project-level in FY12 MyPBAS DB (up to FY15 data) • If SO Forecasts are based on the agreed PDD/MY Budget, keep them at Project-level and simply copy to SO approved commitments until FY15. • If SO Forecasts are not the final agreed amounts, • Either keep them at project-level forecast but reflect agreed PDD/MY budgets at project-level, and copy them to SO commitments at project-level (up to FY15data), or • Change to Programme-level forecast in FY14-16 planning and budgeting process. • From FY16 MyPBAS data, all SOs Forecasts are shown under one project with Programme-level total amount. • Projects that have SO Forecasts at Programme-level in FY12 MyPBAS DB • Keep Programme-level but update to the agreed the total Programme-level amount. • NOs keep to reflect agreed MY Budget to MyPBAS at project-level, and won’t change to the revised CY budget from FY14 MyPBAS. • NOs upload agreed MY Budget into SS budget ledger as ITD Budget from FY14. • If current phase is from FY11-15, upload FY14-15 ITD budget.

  14. Pros and Cons

More Related