1 / 12

The Grand Calorimeter and Trigger Upgrade Schedule Unification Mini-workshop Follow-up

The Grand Calorimeter and Trigger Upgrade Schedule Unification Mini-workshop Follow-up Magnus Hansen 20111109. Disclaimer. The plans and milestones in this presentation are based on Technical constraint Possible performance of the LHC machine Highest availability of CMS for data taking

Télécharger la présentation

The Grand Calorimeter and Trigger Upgrade Schedule Unification Mini-workshop Follow-up

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Grand Calorimeter and Trigger Upgrade Schedule Unification Mini-workshop Follow-up Magnus Hansen 20111109

  2. Disclaimer • The plans and milestones in this presentation are based on • Technical constraint • Possible performance of the LHC machine • Highest availability of CMS for data taking • Spending profiles and some other economical constraints have not been taken into account • Even though no or little additional expenses compared to the minimum are proposed M. Hansen, CERN. magnus.hansen@cern.ch

  3. Introduction, Scope and Goal • That scope and goal for the initial Grand Calorimeter and Trigger Upgrade Schedule Unification workshop was to initiate the discussion such that a synchronized and agreed installation schedule for the three linked subsystems can be finalized during the November Upgrade Week and presented to CMS for approval during the December CMS week. • We are here to receive status and to follow up on items identified during the previous workshop • Calorimeter trigger upgrade progress and plan presentation this afternoon • we should use this opportunity to discuss details M. Hansen, CERN. magnus.hansen@cern.ch

  4. Assumptions - Deductions • Due to the large span of possible LHC machine parameters it cannot be assumed that the current RCT – GCT will be able to cope until LS2 • Foresee operation of an upgraded system before LS2 • The commissioning of upgrades must be planned to keep the risk for CMS availability as low as reasonably achievable at all times • Foresee to commission and operate the complete new trigger in parallel with the current system M. Hansen, CERN. magnus.hansen@cern.ch

  5. Current understanding of LHC schedule • LS1 • Currently scheduled to start December 2012 and last 18 months. • LS2 • Currently scheduled to start December 2018 and last 12 months. • Intermediate extended winter technical stop • Currently not (?) scheduled but likely to start two years into the run period between LS1 and LS2, thus starting December 2016 and lasting up to 6 months. LS1 IETS M. Hansen, CERN. magnus.hansen@cern.ch

  6. Preparation for Upgrade The preparation for the upgrade consists of installing the means required to install, test, and commission the complete upgraded system independently of the CMS operation. • HCAL plan to install optical splitters on the optical fibers from the detector to the HTR cards in order to allow parallel installation, commissioning, and operation of the upgraded off detector electronics system. • The latest date for the re-commissioning of the links to the legacy HTR cards is the end of LS1, 6 months before physics thus leaving time for global commissioning. • ECAL plan to install and commission oSLBs on all TCC cards before the end of LS1, 6 months before physics. • RCT plan to install and commission oRMs on all ECAL locations on RCT receiver cards receiver cards before the end of LS1, 6 months before physics. M. Hansen, CERN. magnus.hansen@cern.ch

  7. Upgrade of Calorimeter Trigger and HCAL Back End • The HF back end will be upgraded first and the plan is to use the upgraded system as the primary for physics after LS1 • Subject to a readiness review and CMS management approval end 2012. • Implies that some additional oRMs are produced and possibly that the initial oRMs are installed in HF positions. • The upgraded calorimeter trigger is planned to be installed and commissioned at the latest when the intermediate extended technical stop starts. • The HCAL Back End installation will be kept in pace with the calorimeter trigger upgrade as it is required for the tests of the trigger path. M. Hansen, CERN. magnus.hansen@cern.ch

  8. Upgrade of the HCAL barrel and end cap front end electronics This is high risk for CMS operation since there is likely no going back. • The R/D necessary will proceed with a pace compatible with complete deployment during the intermediate extended technical stop. • It is however understood that the actual installation may take place later but during LS2 at the latest. • Upgrade of the HO • The upgrade of the HO electronics is imminent and was not discussed in much detail. M. Hansen, CERN. magnus.hansen@cern.ch

  9. Follow-up • HCAL will target to have cost estimates and a rack plan by the FNAL November upgrade workshop. • The target end of production date for all oSLB + oRMs needs to be clarified and the plan should be ready for the November FNAL upgrade workshop. • The details of the oSLB configuration options need to be clarified and should be ready for the November FNAL upgrade workshop. M. Hansen, CERN. magnus.hansen@cern.ch

  10. Today’s discussion: CMS milestones • Proposed CMS milestones • December 2012 • Agree about a common uTCA specification and suppliers • Design a common uTCA rack layout with power supplies and crates • Establish a common maintenance procedure for uTCA equipment • December 2013 • ECAL oSLBs installed and tested • RCT oRMs installed and tested • HCAL front end link splitters installed and tested • June 2014 • ECAL oSLBs connection to oRMs commissioned with CMS global • HCAL front end link splitters connection to HTRs commissioned with CMS global M. Hansen, CERN. magnus.hansen@cern.ch

  11. Today’s discussion: CMS goals • Proposed CMS goals • June 2014 • Demonstrate parasitic operation of a prototype calorimeter trigger slice with inputs from ECAL and HCAL • June 2015 • HCAL back end installation completed • Calorimeter trigger installation completed • December 2015 • HCAL back end commissioned • Calorimeter trigger commissioned • Associated milestones and goals will be developed for GT and muon trigger systems M. Hansen, CERN. magnus.hansen@cern.ch

  12. Discussion M. Hansen, CERN. magnus.hansen@cern.ch

More Related