Estimation. Chapter 3 Applied Software Project Management , Stellman & Greene. Decomposing a project into tasks. By feature By project phase Some combination. The most accurate estimates. Rely on prior experience Teams review previous project results Find how long previous projects took

delora
Télécharger la présentation

Estimation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Estimation Chapter 3 Applied Software Project Management, Stellman & Greene

  2. Decomposing a project into tasks • By feature • By project phase • Some combination

  3. The most accurate estimates... • Rely on prior experience • Teams review previous project results • Find how long previous projects took • Estimates will change because: • People leave the project/get sick • Technical problems arise • Needs of the organization change • The unexpected will almost certainly happen

  4. Two people may disagree on how long a task will take... • Generally because of assumptions on what is required • A good project manager can reduce the uncertainty by creating the vision and scope document

  5. Assumptions • Help when dealing with incomplete information • Should be written down and discussed • Brainstormed by team to identify as many assumptions as possible

  6. Questions to help identify assumptions • Are there project goals that are known to the team, but are not written down? • Are there any concepts, terms, or definitions that need to be clarified? • Are there standards that must be me, but will be expensive to comply with? • How will the development of this project differ from that of previous projects? Will there be new tasks added that were not previously performed? • Are there technology and architecture decisions that have already been made? • What changes are likely to occur elsewhere in the organization that could cause this estimate to be inaccurate? • Are there issues that the team is known to disagree on that will affect the project?

  7. Distrust can undermine estimates • Politics • “Rule” of cutting by third, half... • Lack of trust may cause engineers to inflate their estimates

  8. Wideband Delphi Estimation • Developed in 1940s by Rand Corp. for forecasting • This process produces: • Set of estimates for the schedule • WBS • List of assumptions (for Vision &Scope) • Discussion and time to correct each other • Depends on Vision and Scope document

  9. Delphi Process led by moderator • Kickoff meeting • Create WBS and list of assumptions • After the meeting each member creates an effort estimate for each task • Estimation session • Team revises estimates as a group and reaches consensus • Then project manager summarizes results and reviews with team • See Table 3-1

  10. Details... • Each team member must make an effort to estimate each task honestly • Free flow of information is essential • Sessions can get heated • Include observers to sit in on the meetings: stakeholders, users, managers

  11. Role of the moderator • Should ideally not have a stake in the project • Listens to discussion • Asks open-ended questions • Challenges team to address the issues • Ensures that everyone is contributing

  12. Kickoff meeting • Meeting activities • Moderator explains the process • All read the Vision and Scope if they have not • Moderator goes over the goal statement prepared by the PM and the moderator • Team discusses the product and brainstorms assumptions • Team generates a task list of ~10-20 major tasks => top level of WBS • Team agrees on units of estimation (days, weeks, pages, etc.) • WBS is generated

  13. Individual preparation • Each team member generates a set of preparation results as shown in Figure 3-1 • Task list with units of effort • Calendar waiting time • Project overhead tasks

  14. Estimation session • Members bring their individual work and ... • Fill out estimation forms as in Figure 3-2: one row for each task and totaled • Moderator collects and plots totals on a line: Figure 3-3 • Each estimator gives clarification and changes to the task list • Team resolves issues or disagreements • Estimators revise their estimates by filling in the next Delta column • Cycle repeats until agreement or two hours

  15. Assembling tasks and Reviewing results • Figure 3-5 shows each estimator’s final estimates • Best and worst cases are shown • Assumptions are put in final form and now entered into Vision and Scope • What happens when one team member continues to disagree?

  16. Other Techniques • PROBE • COCOMO II • The Planning Game • For Next Time: • Vision and Scope • Readings