MicroBooNE Working Group Meeting

MicroBooNE Working Group Meeting. March 22, 2011 1 :00 – 2:00 PM Black Hole (WH2NW). Agenda. WBS 1.4 – TPC System Progress Report [Bonnie Fleming] WBS 1.5 – Readout & DAQ Progress Report [Cat James for Hucheng Chen] WBS 1.8 – PMT System Progress Report [ Arati Prakash ]

tass
Télécharger la présentation

MicroBooNE Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MicroBooNE Working Group Meeting March 22, 2011 1:00– 2:00 PM Black Hole (WH2NW)

  2. Agenda • WBS 1.4 – TPC System Progress Report [Bonnie Fleming] • WBS 1.5 – Readout & DAQ Progress Report [Cat James for Hucheng Chen] • WBS 1.8 – PMT System Progress Report [AratiPrakash] • Project Status Report [Cat James] • Preparations for Director’s CD-2/3a Progress Review [Dean Hoffer/Greg Bock/Cat James/All] • Next Meeting • Action Items 22-Mar-2011 MicroBooNE WGM

  3. Preparations for the Director’s Review • Charge Revised • Agenda Revised • Review Team Established • March 18 Documentation Posting • Inquiring on Dinner Attendance 22-Mar-2011 MicroBooNE WGM

  4. Review Team • Ron Ray – Chair • Mike Crisler • George Ginther • Marc Kaducak • Russell Rucinski • Peter Shanahan • Bob O’Sullivan • Jason Budd • Jesse Adams 22-Mar-2011 MicroBooNE WGM

  5. Next WGMs • 12-April– Post Review Actions and WBS 1.2 - Cryogenics Systems Progress Report [Jim Kilmer] WBS 1.3 – Cryostat System Progress Report [Craig Thorn] WBS 1.6 – Experiment Infrastructure Progress Report [Dixon Bogert] • 26-April– Post Review Follow-up and WBS 1.4 – TPC System Progress Report [Bonnie Fleming] WBS 1.5 – Readout & DAQ Progress Report [Hucheng Chen] WBS 1.8 – PMT System Progress Report [AratiPrakash] 22-Mar-2011 MicroBooNE WGM

  6. Action Items Open Items from Last WGM: • Cat- Generate and distribute narrative month project report. • Dean – update draft agenda and resend to MicroBooNE and Greg Open Items from Prior Meetings: • Greg/Mike L. – address engineering needs for WBS 1.2 22-Mar-2011 MicroBooNE WGM