1 / 25

Asbestos in Soil

Asbestos in Soil. Greg Holt Stapleton Redevelopment Program City and County of Denver October 3, 2008. Stapleton Redevelopment . Stapleton Airport closed in 1995 Largest Brownfield Urban Project 4000 Acres 2900 acres Developable 1100 acres Open Space Redevelopment began in 1998

Lucy
Télécharger la présentation

Asbestos in Soil

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Asbestos in Soil Greg Holt Stapleton Redevelopment Program City and County of Denver October 3, 2008

  2. Stapleton Redevelopment • Stapleton Airport closed in 1995 • Largest Brownfield Urban Project • 4000 Acres 2900 acres Developable 1100 acres Open Space • Redevelopment began in 1998 • Three programs: Environmental Demolition Airfield Pavement Removal

  3. Development • Land Transfer Environmental Standards • Stapleton Numeric Criteria-SNC • City, EPA and State of Colorado • Certification from Property Owner • NFA/NAD for Environmental Sites • Approximately 120 NFA’s received • Master Developer Chosen

  4. Asbestos Under Regulation 8 • 125 Building abated prior to demolition • 50% of the Fuel Distribution System • Utilities: Water Electric Communication/ Telephone

  5. Asbestos in Soil • Lowery and Buckley • Regulation Change - May 2006 • Land Transfer Requirements • Industry Changes • Environmental Site Assessments • Sophistication of Asbestos Abatement Contractors • Close out reports / NFA Requests

  6. Highline Canal Phase 1 Filing 16 History • City Purchased the land for airport expansion mid 1950’s • Lateral of the Highline canal • Canal backfilled with mixed waste • Overall site was backfilled for runway expansion-mid 1960’s

  7. Filing 16 Timeline • Environmental Assessments- 6/04 and 1/05 • Site Characterization- Summer 2005 • Work Plan Approved by CDPHE - Fall 2005 • Insurance Acceptance of Claim Fall 2005 • Project Bid - November 2005 • Contractor Selected - January 2006 • NTP – March 2006 • Abatement – April 2006- Current

  8. Filing 16 2006

  9. Filing 16 - 2008

  10. Filing 16 Timeline • Work Plan Approved by CDPHE - Fall 2005 • Joint meeting with CDPHE - March 2006 • Original Work Plan amended 3 times • Development of site wide work plan • Creation of Clearance Protocol -Fall 2006 • Suspension of Work Plan- October 2008

  11. Filing 16 • Original Scope of Work • Est. 120,000 yds • 70,000 yds Non- Friable ACM • 50,000 yds Friable ACM • Area approximately 40 acres • Duration 180 days • Actual • Est. 730,000 yds • 480,000 yds Non- Friable ACM • 250,000 yds Friable ACM • Area increased to 105 acres • Duration 29 months

  12. Filing 16

  13. Filing 16

  14. Filing 16

  15. Filing 16

  16. Filing 16

  17. Filing 16

  18. Filing 16

  19. Filing 16 Suspension of Work • Why? • City reached Sitewide Cap on costs • Insurance reimbursement • Slow in payments • Payments in arrears.

  20. Filing 16 Suspension of Work Site Status • Canal Cleared • 88% of the total site has been cleared • 15% of the site has been backfilled • Remaining area is under a stockpile.

  21. Filing 16 Suspension of Work • Site Security • Site Stabilization • Protection of Human Health and Environment • Air Monitoring

  22. Filing 16 Insurance Reimbursement • Original Scope of Work $7,000,000.00 • Estimate to Completion $50,000,000.00

  23. Stapleton Asbestos • One site complete - closure report and NFA submitted • Two sites complete –awaiting submittal • Two sites in progress • Five sites not started

  24. Stapleton Lessons learned • Site size- • Unit pricing • Type of equipment to be used • Wetting methods • Material – • Friable • Non-Friable • Mixture • Mechanical means • Use of excavators, graders, other heavy equipment • Soil preparation • Methods to achieve “adequately wet”

  25. Stapleton Questions

More Related