1 / 22

Sand & Gravel and Asphalt Plant Permitting

Sand & Gravel and Asphalt Plant Permitting. R K “Chip” Hancock III, P.E. Construction Permit Unit Supervisor Air Pollution Control Division. Reporting and Permitting (Regulation #3). Required to Report – ie submit Air Pollutant Emission Notice (APEN): Gravel Pits

Samuel
Télécharger la présentation

Sand & Gravel and Asphalt Plant Permitting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sand & Gravel and Asphalt Plant Permitting R K “Chip” Hancock III, P.E. Construction Permit Unit Supervisor Air Pollution Control Division

  2. Reporting and Permitting (Regulation #3) • Required to Report – ie submit Air Pollutant Emission Notice (APEN): • Gravel Pits • Note: APEN for mining operations includes fugitive dust control plan • Asphalt Plants • Diesel Generators (some older units and non road may be exempt) • Crushers and Screens • Most Concrete Plants

  3. Required to get a “construction permit” prior to construction and operation • Gravel Pits with  70,000 tons per year of production • Asphalt Plants • Diesel Generators • Crushers and Screens • Many Concrete Plants

  4. Permits are issued as Initial Approval • Allows source to construct and begin operating • Needed for Final Approval: • Construction must begin within 18 months of: • Permit issuance, or • Start of construction date stated on application, • Construction must be completed in a reasonable time (due diligence) • The following must be completed, and submitted to the Division within 180 days of start up: • Opacity Measurements on asphalt plants, engines, and processing equipment • Self Certification of Compliance Form • Stack Testing of Asphalt Plant results to Division (protocol due at least 30 days before test)

  5. Permit Timing • Division is allowed 90 days from the receipt of a complete application • Division is allowed 60 days to determine if the application is complete (concurrent with the 90 days if the application is complete when received) • If public comment is need there is an additional 45 days • Actual controlled emissions of any one criteria pollutant of 50 tons per year or more (25 for NOx or VOCs in the Non-Attainment Area) • Synthetic Minors – large number of asphalt plants are in this category • Division Discretion – based on anticipated public concern, location, amount and type of emissions, etc.

  6. Impact Modeling • Used to demonstrate compliance with the National Ambient Air Quality Standards (NAAQS). • For Asphalt Plants – Required for Major sources and those few minor sources where the emissions exceed the PSD major source significance levels • For Gravel Pits - Usually only required if controlled PM10 emissions exceed 82 pounds per day or 15 tons per year (per the Division’s Modeling Guidance) – so usually only required for the larger pits

  7. Preemption • There is no preemption in the state regulations. • County (or City) can promulgate any rules or regulations on air pollution. • The local agency would be responsible for enforcement of their rules. • The following are the only Cities or Counties I am aware of that have developed or considered developing their own rules: • El Paso County Fugitive Dust permitting • City of Lakewood Crematories • Boulder County Fugitive Dust

  8. Portable Units • Asphalt Plants, Concrete Plants, Generators, and Processing equipment can be permitted as portable (must request on APEN) • Cannot stay in one location for more than 2 years – otherwise the unit is considered stationary • Must submit 10-day notice of relocation form prior to moving to a new site

  9. Permit Modifications • The following would require modification of permit: • Prior to exceedence of any permit limit • Use of a fuel type not currently included on permit • Use of recycled asphalt (if not already included on permit) • Changing or addition of air pollution control equipment (this would include the addition of silo(s))

  10. Permit Mods. Continued • The following would require the issuance of an entirely new permit: • Replacement of unit – this would include drum replacement (ie: changing the serial number of the unit) • Changing from portable to stationary or stationary to portable • Relocation of a stationary source

  11. Used Oil • Can be used as a fuel type if included in permit. • Can not burn off-specification used oil. Off-specification oil is considered hazardous waste fuel and can therefore be burned only in a RCRA permitted incinerator.

  12. Used Oil Specifications If the oil exceeds any of the following, it is considered off-specification: compound limit Arsenic 5 ppm Cadmium 2 ppm Chromium 10 ppm Lead 100 ppm total halogens: 1000 ppm In addition, the flash point shall be greater than or equal to 100 degrees F.

  13. NSPS Subpart IIII • All new (or new to Colorado) diesel engines must meet the new Federal NSPS. • The only exemption is for non-road engines • If an engine is at any one location for more than 1 year it is not a non-road engine. • All engines subject to the NSPS need construction permits regardless of emission levels – the exemptions no longer apply.

  14. Odors (Regulation #2) • First page of Regulation #2 – the rest only applies to hog farms.

  15. Emission Calculations • Asphalt Plants • Use AP42 emission factors and equations and CO emission factors developed by the Division based on stack test data (PS memo 96-07) • Various emission factors and equations involved • Some of the factors have very low ratings – so on occasion the Division may adjust some of these factors • Asphalt Plant spreadsheet

  16. Emission Calculations, Cont. • Gravel Pits • Use AP42 emission factors and equations • Many emission factors. They come from more than one AP42 chapter • Crushed Stone Processing • Coal Mining • Unpaved Haul Roads

  17. Emission Calculations, Cont. • Diesel Generators • Manufacturer’s emission factors or NSPS IIII allowable emission factors • Normally use whichever is lower • Some engines can pass the NSPS levels, but actually have higher emission factors

  18. Emission Calculations, Cont. • Concrete Plants • AP42 factors • Spreadsheet similar to Asphalt Plant, but simpler

  19. Emission Calculations, Cont. • Crushers and Screens • AP42 – Crushed Stone Processing • Use screening factors and tertiary crushing factors • back calculate control efficiency using wet vs. dry factors • NSPS OOO pulls most into needing construction permits

  20. Websites • APCD - Stationary Sources: http://www.cdphe.state.co.us/ap/stationary.html • Permitting/APEN forms: http://www.cdphe.state.co.us/ap/downloadforms.html • Regulations:  http://www.cdphe.state.co.us/regulations/airregs/index.html • Modeling Guidance: http://colorado.gov/airquality/permits.aspx

  21. Permitting/Engineering Contacts • R K "Chip" Hancock III, P.E. (303)-692-3168 • Construction Permits Unit Supervisor • r.hancock@state.co.us • Stationary Sources Program (303)-692-3150

  22. Enforcement Contacts • Bob Jorgenson (303)-(303)-692-3171 • Field Services Unit Supervisor • Paul Carr (303)-(303)-692-3250 • Supervisor • Shannon McMillan (303)-(303)-692-3259 • Supervisor

More Related