1 / 7

US Stave Core Production

US Stave Core Production. D. Lynn (BNL), LBNL Mechanical Meeting, Sep 2012. US Stave Fabrication Sequence. Differs mostly from UK sequence in that we pre-machine foam and make foam-pipe assembly Do we need identical standardized assembly of stave core in production?. UK Foam Split.

adolfo
Télécharger la présentation

US Stave Core Production

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. US Stave Core Production D. Lynn (BNL), LBNL Mechanical Meeting, Sep 2012

  2. US Stave Fabrication Sequence • Differs mostly from UK sequence in that we pre-machine foam and make foam-pipe assembly • Do we need identical standardized assembly of stave core in production? UK Foam Split US Foam Split

  3. Assembly Sequence and Institutions for US Stave Cores Built Up to Now • LBNL fabricates facings (either standard or co-cured). Ships to BNL • BNL glues CF tubes, foam-pipe assembly, honeycomb to first facing, and end closeouts . Ships to Yale • Yale grinds honeycomb. Ships to BNL • BNL glues last facing • Characterization (or QA) at BNL • Expect facings will continue to be fabricated at LBNL • All of the other steps could in principle be done at any of these institutions • E.g. at present we do grinding at Yale as they have access to own grinder, but at BNL our central machine shops can do it (for prototyping, they are way too expensive!) • Is it possible to skip grinding in future? (or perhaps use corrugated core??)

  4. Old Gantt Chart (2009) for Stave Core Assembly—I have not updated it

  5. Old Gantt Chart (2009) for Stave Core Assembly—I have not updated it • Chart implied ~ 3 weeks assembly and QA (not including facing fabrication). • Expect to maintain a throughput of 1/day (although maybe could do 2/day without much additional effort?). • Seems likely need at most two main centers of production (US and UK). • Where in US to make stave cores will require a comprehensive look at where hybrids, modules, stave cores, and final module mounting and stave testing will be done to maximize utilization of resources within US community – also will depend upon funding.

More Related