230 likes | 359 Vues
This document provides a comprehensive review of the DBSP-R upgrade progress as of January 6, 2011, highlighting significant advancements in optics, mechanics, electronics, and software. Key improvements include increased quantum efficiency, doubled spectral length, and enhanced user experience with lower noise levels and improved cooling performance. The report details the status of optics shipping, dewar body orders, as well as internal and external electronics developments. Critical milestones are also outlined for the upcoming deployment and testing phases of the upgraded system.
E N D
DBSP-R Progress Review DBSP-R UpgradeProgress Review 2011-01-06 The DBSP-R Team
Motivation for the Upgrade DBSP-R Progress Review • Much greater QE at reddest wavelengths. • Spectral length doubled. • Improved ease of use. Additional benefits: • Lower noise (<2.5e- @20s read time) • 15µm pixels instead of 24µm; low lateral charge diffusion. • No fringing. • Standardization of electronics and software. • Improved LN2 hold time (30+ hours).
DBSP-R Progress Review Optics
Optics (Viswa) DBSP-R Progress Review • Window lens specs as per Epps’ design (originally for flat CCD, like ours). • Status: • Flat window (for testing) in hand. • Lens window shipped from HJOL to coating company. Expected next week.
DBSP-R Progress Review Mechanical
Mechanical – Dewar Body DBSP-R Progress Review • Dewar ordered form IR Labs. • Vendor compliance checked. • Expected: first week of February.
Mechanical – Dewar Base (Khanh) DBSP-R Progress Review • Basic design: DONE. • Detail drawings in progress.
Mechanical – Flexure FEA DBSP-R Progress Review Aluminum rings • Mass mounting surface : • Detector mask : .4 lb • Cold shield : .3 lb • Detector standoff assy : .6 lb • (including detector package) Total deflection of 0.6µm with the mass of 1.3 lbs Cable feedthrought holes Spacer G-10 CR,.020” thk sheet Total deflection of 5.5µm with the mass of 13 lbs
Mechanical – Detector Mount DBSP-R Progress Review Detector support areas Flexure mount mount pocket Detector mount plate Spring leaf
Mechanical – Head Installation Proc • Sliding the detector standoff assy • over the two guiding shafts for • installation from the back of dewar • base. • Sliding the detector mask • over the two guiding shafts for • installation from the front of dewar • base.
Mechanical – Detector Electronics Box DBSP-R Progress Review • Modifications for patch panel: DONE. • Mounting assembly: Released for fab.
DBSP-R Progress Review Electronics
Electronics - External DBSP-R Progress Review • Detector Controller + Boards in the lab: in testing. • Patch Panel Board: in fabrication. • Heater PCB: template from Antarctic camera. • Controller Box wiring: • Boards to Patch Panel. • Hermetic connectors to Patch Panel. • Cables: • Dewar to Cass Cage Rack.
Electronics - Internal DBSP-R Progress Review • Fanout PCB: to be designed. • Internal wiring: • Fanout Board to hermetic connectors. • Detector mount temperature control. • Dewar body temperature control.
DBSP-R Progress Review Computer and Software
Computer and Software (Jennifer) DBSP-R Progress Review TCP/IP sockets PCI Driver • Only the communication between the ArcVIEW server and the interface driver (PCI vs. EDT) changes in the new architecture. • The new DBSP RED ArcVIEW server is essentially identical to the current DBSP BLUE ArcVIEW server except for detector specific configuration parameters. Custom C code DBSP BLUE ArcVIEW Server TCP/IP sockets Sync Module DBSP BLUE GUI interface DBSP RED GUI interface PCI Driver TCP/IP sockets Custom C code DBSP RED ArcVIEW Server Aux Monitor GUI interface Auxiliary Monitor ArcVIEW Server TCP/IP sockets
Computer, OS and Dev Tools DBSP-R Progress Review • The computer used for deploying DBSP-RED will be one of a set of 5 identical computers installed at the observatory to upgrade the instrument computer infrastructure. Systems already delivered, installed and operational • A laboratory version of the instruments computers used at the observatory has been built with identical hardware and software to use as a development platform at Caltech. Hardware assembled, cloning completed • Replace the current DBSP RED ArcVIEW server with a copy of the DBSP BLUE server and then configure for the new detector. Development code assembled and under version control • Advantages • Maintains a consistent software architecture for the DBSP instrument at the observatory. • Eliminates the risk inherent in deploying a new solution. • Minimizes the time required to develop the software for the instrument.
Projected Deployment Sequence DBSP-R Progress Review • Develop with the laboratory computer • Deliver the laboratory computer to the observatory. • Deploy the DBSP_RED2 code developed at Caltech onto the existing instrument computers as test in tandem with the development computer. • Delivery to the observatory should consist of a new version of the ArcVIEW server configured for the new detector that will simply replace the contents of the existing DBSP/RED directory. - Actually create a new DBSP/RED2 instrument
DBSP-R Progress Review Management
Schedule – Lab activities DBSP-R Progress Review Critical milestones: Fab Jan • Dewar body: Feb 4 • Dewar base: Feb 20 Feb • Fanout PCB: Feb 25 Integ • Dewar assembled: Feb 25 Mar Test • Detector warm test: March 4 • Detector cold test: March 11 Apr • Pre-ship Review: April 25 • Off-telescope test: April 27 Tel May • First Light: May 4
Schedule - Commissioning DBSP-R Progress Review • Pre-installation (off-telescope): April 28-30. • Cass cage rack modules (Leach power, Lakeshore, connector plate). • Cables. • Palomar staff support required. • Mount dewar and run tests with calibration lamps (some risk for incoming observers…) • First commissioning: May 4 or 5. • Measure throughput and flexure/tilt with standard stars. • Second commissioning (if necessary): July 2 or 3.
Budget DBSP-R Progress Review • Expenditures through early December 2010: • Materials = $36K (controller, mechfab) • Labor = $142K • Commitments = $25K (dewar, optics, Lakeshore) • Budget FY10 = $260K • Available = $57K • Projected expenditures: • Labor (team) = $130K • Projected Materials (shop fab) = $6K (106 hours) • Deficit = $79K
Budget – Projected Team Load DBSP-R Progress Review Projected Labor Cost = $130K