SlideServe
Menu
Préférences
© SlideServe · v2026

Transportation Problems

allen-diaz avatar
30 diapositives · 672 Views · Nov 11, 2014

Transportation Problems. Tableau Shipping Solutions NorthWest Corner Rule Stepping Stone Algorithm. Transportation Problems. Have suppliers, users, shipping costs. Tableau: displays info with rim conditions . Each cell has two entries: costs and amount to ship.

Transportation Problems - slide 1
01 / 30Transportation Problems
1 / 17

Télécharger la présentation

Transportation Problems
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Transportation Problems Tableau Shipping Solutions NorthWest Corner Rule Stepping Stone Algorithm Mathematics in Management Science

  2. Transportation Problems Have suppliers, users, shipping costs. Tableau: displays info with rim conditions. Each cell has two entries: costs and amount to ship. Shipping solution: obeys all constraints. NorthWest Corner Rule: an algorthim for obtaining a shipping solution. Indicator Values: Stepping Stone Algorithm.

  3. Bakery Example Chain gets bread deliveries from a bakery chain that does its baking in different places. Each store needs certain number of loaves/day. Supplier bakes enough to exactly meet demands. How many loaves should be to stay within the demands and to minimize the cost?

  4. Mines & Plants Two mines (extract/supply ore) and three plants (process/demand ore). Mine A supplies 7 m tons, B 3 m tons. Plant 1 needs 2 tons, 2&3 each 4 tons. Shipping costs are from A to P1,P2,P3 --- 7, 1, 3 from B to P1,P2,P3 --- 9, 5, 12

  5. Suppliers on left; demanders on top. Next add rim conditions: Supply amounts in last column. Demand amounts in last row. Check that amounts agree!

  6. Next add shipping costs. Cell (m,p) is cost to ship from mine m to plant p.

  7. Need shipping solution to start with.

  8. NorthWest Corner Rule Locate top far-left-hand cell. Ship via this cell with smaller of the two rim cells (call the value s) ; circle entry in tableau. Cross out row or column with rim value s, & reduce other rim value for this cell by s. When a single cell remains, shud be tie for rim conditions of row and column involved; put this amount into cell and circle.

  9. Here!

  10. Cost=14+4+3+36=57

  11. Check Indicator Values