Phase 4 Installation of Undulator Magnet Power Supplies: Comprehensive Overview
This document outlines the Phase 4 installation program for Undulator Magnet Power Supplies (PS) led by Antonio de Lira and Kristi Luchini. It includes the overall scope of the installation, rack profiles, system characteristics, and detailed scheduling from initial site visits to completion. The agenda covers critical elements, including controls, open items, and equipment status for both B913 and B921 systems, ensuring a thorough understanding of the installation requirements, procurement status, and electrical interconnections.
Phase 4 Installation of Undulator Magnet Power Supplies: Comprehensive Overview
E N D
Presentation Transcript
Undulator Week 3 Magnet Power Supplies Phase 4 Installation Antonio de Lira Kristi Luchini
Undulator Magnet PS Phase 4 InstallationAgenda • Installation Program - Scope • Rack Profiles & System Characteristics • Overall Schedule • Open Items • Magnet PS Controls By Kristi Luchini
Undulator Magnet PS – PH4 Installation ProgramOriginal Scope • B913 – UND • 54 MCORs • 18 QUAD – MCOR6 • 36 X/YCOR – MCOR1 – Not part of Phase IV • B921 – UND + DUMP • 45 MCORs • 15 QUAD – MCOR6 • 30 X/YCOR – MCOR1 – Not part of Phase IV • 03 Intermediate PS – DUMP • 06 MCORs – DUMP
54 MCORs - UND 18 QUAD – Phase IV 36 X/YCOR (?) 45 MCORs – UND 15 QUAD – Phase IV 30 X/YCOR (?) 03 Intermediate PS – DUMP 06 MCORs – DUMP Undulator Magnet PS - PH4 Installation Program B913 B921
Undulator Magnet PS Installation Program – B921 03 Intermediate 45 MCORs – UND 06 MCORs - DUMP
Undulator Magnet PS – Electrical Interconnections Undulator magnet PS are NOT interlocked (except for GND fault)
Schedule • Overall Schedule • Magnet PS Cable Plant (Phase 4) Ponce Rodriguez – This review • 01/30/08 Site Visit • 02/19/08 Bid Opening • 03/04/08 Award • 04/01/08 Installation Start • 10/31/08 Installation Complete • Detailed schedule • Integrated with Project Office’s Installation Schedule
Equipment Status / Rack Readiness B913 B921
Open Items • 66 MCORs for UND correctors • MCOR modules to come from PEP • MCOR modules have been requested already • D. MacNair has a new design for a MCOR1 • No performance requirements document • PCD will assume 25 ppm/C is fine Note: Support buildings will have temperature control: 75 ± 5F
Undulator Magnet PS - Controls • Magnet PS Control Systems • Kristi Luchini
Magnet PS ControlsProcurement Status * Equipment within PS racks
Magnet Magnet EPICS IOC MCOR VME Crate System Architecture OPI OPI Ethernet Timing (Fiber Optic) 16 Magnets@ 6 Amps max Note: configure for 1 or 6 A Terminal Server PLC PS Protection System Bulk PS
Software • IP Addresses Network Nodes – Done • Software – Done (for 10Hz feedback) • Databases - April 28 to May 10, 2008 • polynomials (I vs B) as magnets are measured. • Displays • B913: Complete May 5, 2008 • B921: Complete May 10, 2008 • Pre-Installation checkout in B15 • B913: May 10-15, 2008 • B921: May 15-20, 2008 • System Checkout - Network checkout and system integration • B913: Oct 31 - Nov 11, 2008 (54 MCORs), Install racks July 10-15 • B921: Oct 29 – Dec 4, 2008 (45 MCORs), Install racks July 22-30