An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Assessing Potential Health Risks of Metals in Residential and Recreational Area Near the U.S.-Canadian Border Lake Roosevelt Forum Laura Buelow, Ph.D., R10 U.S. EPA, Hanford Project Office

  2. Northport Removal Action • In 2004, EPA initiated a removal at the Le Roi smelter • 29 properties had soil removed • 94 properties had exposure reduction measures • 65 properties had no action

  3. Two Different Soil Sampling Plans • Upland soils • Teck is lead, EPA approves sampling plan • Human health and ecological • Broader scope • Residential • EPA is lead • Specific to properties in sampling area that have residences • Human heath focused

  4. Goal of Upland Soils Study • Determine where there may be harmful levels of metals in soil from smelter impacts and define the outer limit of concentrations which could cause problems to people or the environment. • Collect data to evaluate human health and ecological risks associated with contaminants in uplands soil

  5. Schedule for Upland Soils • Teck to submitted Draft Sampling Plan to EPA in September 2013 • EPA (and Participating Parties) are currently reviewing Sampling Plan and will submit comments in December • Goal is to finalize Sampling Plan by spring 2014 and start sampling summer 2014. Sampling may extend into 2015.

  6. Residential Soil Sampling • Ecology report gave enough data for EPA to prioritize a Residential Soil Sampling program • EPA is drafting the sampling plan

  7. Residential Soil Sampling Schedule • Fall 2013- contact land owners, develop general sampling plan • Informal notice letting landowners know they are in the area of interest for sampling (to be sent in next couple weeks) • Formal Access Agreement will be sent requesting permission to sample property (December) • Winter to Spring 2014- finalize general sampling plan • Spring 2014 – property visits to develop sampling plan specific to each property • Summer/Fall 2014- sample properties

  8. Questions?