An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COMP 4300 Computer ArchitectureDatapath Dr. Xiao Qin Auburn Universityhttp://www.eng.auburn.edu/~xqin xqin@auburn.edu Fall, 2010

  2. Datapath for Branch Instructions beq rs, rt, offset • if (R[rs] == R[rt]) then PC ← PC+4 + s_extend(offset<<2)

  3. Datapath: More Detailed View

  4. Simple Implementation • Include the functional units we need for each instruction

  5. RTL Code for MIPS add • Fetch Instruction = ROM[PC], PC=PC+4 • Read Operands ALUOp1 = Registers[rs-value], ALUOp2 = Registers[rt-value] • Add ALUOut = ALUOp1+ALUOp2 • Write Result Registers[rd-value] = ALUOut

  6. R1 P C R2 Inst. address R3 Add (control signals) Data Port#1 WriteRegister ReadRegister#1 Port#2 ReadRegister#2 ALU Datapath Components for MIPS add add R1, R2, R3

  7. R1 P C R2 Inst. address R3 add Data Port#1 WriteRegister CLK ReadRegister#1 Port#2 ReadRegister#2 ALU Datapath Connections for MIPS add add R1, R2, R3 Interconnections What is missing?

  8. R1 P C R2 Inst. address R3 add Data Port#1 WriteRegister ReadRegister#1 Port#2 ReadRegister#2 ALU Critical Path for MIPS add add R1, R2, R3 CLK Interconnections Critical path

  9. R1 P C R2 Inst. address -100 lw/sw Data Port#1 WriteRegister ReadRegister#1 Port#2 Address ReadRegister#2 16 32 SIGN-EXTEND DataOut ALU DataIn RAM Datapath Components for MIPS lw/sw lw R1, -100(R2) sw R1, -100(R2) 16 ROM Instruction Memory REGISTERS Data Memory

  10. R1 P C R2 Inst. address -100 lw Data Port#1 WriteRegister ReadRegister#1 Port#2 Address ReadRegister#2 16 32 SIGN-EXTEND DataOut DataIn RAM Connections for lw lw R1, -100(R2) ALU 16 ROM Instruction Memory REGISTERS Data Memory

  11. R1 (rt) P C R2 (rs) ALU Inst. address 16 (Imm) -100 ROM Instruction Memory REGISTERS lw Data Port#1 WriteRegister ReadRegister#1 Port#2 Address ReadRegister#2 16 32 SIGN-EXTEND DataOut DataIn RAM Data Memory Critical Path for lw lw R1, -100(R2)

  12. R1 P C R2 Inst. address -100 sw 16 32 SIGN-EXTEND Connections for sw sw R1, -100(R2) Data Port#1 WriteRegister ALU ReadRegister#1 16 Port#2 ROM ReadRegister#2 Instruction Memory REGISTERS Address DataOut DataIn RAM Data Memory

  13. R1 P C R2 Inst. address -100 sw 16 32 SIGN-EXTEND Critical Path for sw sw R1, -100(R2) Data Port#1 WriteRegister ALU ReadRegister#1 16 Port#2 ROM ReadRegister#2 Instruction Memory REGISTERS Address DataOut DataIn RAM Data Memory

  14. P C P C R1 R1 Inst. address Inst. address R2 R2 R3 -100 lw add lw R1, -100(R2) Data Data Port#1 Port#1 WriteRegister WriteRegister ALU ReadRegister#1 ReadRegister#1 16 Port#2 Port#2 SIGN-EXTEND Instruction Memory ReadRegister#2 ReadRegister#2 16 32 Address DataOut ALU DataIn RAM Data Memory Datapath Connections for MIPS add and lw add R1, R2, R3 CLK

  15. NEED MUX P C R1 ALU Inst. address 16 R2 Instruction Memory -100 lw Data Port#1 WriteRegister ReadRegister#1 Port#2 SIGN-EXTEND ReadRegister#2 16 32 Address DataOut DataIn RAM Data Memory Datapath Connections for MIPS add and lw

  16. NEED MUX P C R1 ALU Inst. address 16 R2 Instruction Memory -100 lw Data Port#1 WriteRegister ReadRegister#1 Port#2 SIGN-EXTEND ReadRegister#2 16 32 Address DataOut DataIn RAM Data Memory Combined Datapath: R-Type and Load/Store Instructions

  17. Combined Datapath: Executing an R-Type Instruction add rd,rs,rt

  18. Combined Datapath: Executing a load instruction lw rt,offset(rs)

  19. Combined Datapath: Executing a store instruction sw rt,offset(rs)

  20. Summary • Read Ch B.7-9