SlideServe
Menu
Préférences
© SlideServe · v2026

Electric Field Instrument (EFI) Development Schedule and Component Status Overview

bary avatar
4 diapositives · 188 Views · Oct 09, 2014

This document outlines the development schedule and component status of the Electric Field Instrument (EFI). It details the timelines for mechanical and electrical preamp completion, as well as progress on related assemblies including BEB, BMD, SPB, and AXB. Key long-lead parts are highlighted, with procurement timelines noted. The schedule spans from August 2003 through June 2004, providing an overview of fabrication, assembly, and testing phases. This comprehensive schedule serves as a reference for project tracking and milestone fulfillment.

Electric Field Instrument (EFI) Development Schedule and Component Status Overview - slide 1
01 / 4Electric Field Instrument (EFI) Development Schedule and Component Status Overview
1 / 17

Télécharger la présentation

Electric Field Instrument (EFI) Development Schedule and Component Status Overview
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Electric Field Instrument (EFI) • Schedule

  2. Schedule (1) • Design (Definition and BB) • Preamp Mechanical (Aug-Oct ’03; complete). • Preamp Electrical (Aug-Oct ’03; complete). • BEB (Jul-Oct ’03; complete). • BMD (Sep ’03; complete). • SPB (Aug ’03 – Jan ’04; 50%). • AXB (Jun ’03 – Dec ’03; 50%). • Long-Lead Parts: • AXB stacers (ordered Sep ’03; 12-wk lead time) • SPB wire cable (RFQ issued Oct ’03; 6-wk lead time) • SPB motors (RFQ issued Oct ’03; 13-wk lead time)

  3. Schedule (2) • EM/ETU • SPB • Mach, Nov-Dec ’03; Assy, Dec ’03 – Jan ’04; Test, Feb ’04. • AXB • Mach, Dec ’03 – Jan ’04; Assy, Feb ’04; Test, Feb ’04. • Preamp (Mechanical and Electrical) • Layout/Fab/Assy, Oct ’03 (now!); Test, Nov ’03. • BEB • Layout/Fab, Oct-Nov ’03; Build, Nov ’03; Test, Dec ’03. • BMD • Layout/Fab, Nov ’03; Build, ’03; Test, ’03.

  4. Schedule (3) • Flight • SPB • Mach, Jan-Feb ’04; Assy, Mar-May ’04; Test, May-Jun ’04. • F1 schedule; F2-F6 follow 1-mo intervals, Jun-Oct ’04). • AXB • Mach, Feb-Mar ’04; Assy, Apr-May ’04; Test, May ’04. • F1 schedule; F2-F6 follow at 2-wk intervals, Jun-Sep ’04). • Preamp • Layout/Fab, Nov ’03-Jan ’04; Assy, Jan-Feb ’04; Test, Feb ’04. • F1 schedule; F2-F6 at 2-wk intervals, Feb-Apr ’04). • BEB • Layout/Fab, Jan-Feb ’04; Build (all), Mar-Apr ’04; Test, Mar ’04. • F1 schedule; F2-F6 at 1-wk intervals, Mar-Apr ’04. • BMD • Layout/Fab, Jan-Feb ’04; Build (all), Mar-Apr ’04; Test, Mar ’04. • F1 schedule; F2-F6 at ~1-wk intervals through Mar-Apr ’04.