Join us on Tuesday, July 17 from 7pm to 10pm to learn how to create a comprehensive Software Quality Assurance (SQA) plan for a dental office software. This session will guide you through setting up standards and project documents, with a focus on team structures and performance metrics like Earned Value Analysis. Dive into budgeting, progress indicators, and more. Don't miss this valuable opportunity to enhance your software development skills!
Interactive Session: Building SQA Plan for Dental Software
E N D
Presentation Transcript
Interactive Session 4 • Tuesday, July 17 7pm to 10pm • Build a sqa plan for the dental office software • Assume a 3-person, development team, a separate 2-person, test team, and a project manager above the dev team’s manager • Assume a reasonable set of company standards and a reasonable set of project documents
SQA Plan • This is a example of an SQA plan. • See lecture page for link
Final Exam Preview Final Exam, Thursday, July 26
Earned Value Analysis Basing Progress on Percentage of Estimated Effort
Basic Measures (1) • Budgeted Cost of Work(BCW): the estimated effort for each work task. • Budget at Completion (BAC): the sum of each BCW and thus the estimate of the total effort for the project • Planned Value (PV): the percentage of the total estimated effort that is assigned to a particular work task. PV = BCW/BAC
Basic Measures (2) • Budgeted Cost of Work Scheduled (BCWS): the sum of the estimated effort for each work task that was scheduled to be competed by the specified time. • Budgeted Cost of Work Performed (BCWP): the sum of the estimated efforts for the work tasks that have been completed by the specified time.
Basic Measures (3) • Actual Cost of Work Performed (ACWP): the sum of the actual efforts for the work tasks that have been completed.
Progress Indicators (1) • Earned Value(EV) = BCWP/BAC = the sum of the PV’s for all completed work tasks • Schedule Performance Index (SPI) = BCWP/BCWS • Schedule Variance (SV) = BCWP – BCWS
Progress Indicators (2) • Percent Complete (PC) = BCWP/BAC • Cost Performance Index (CPI) = BCWP/ACWP • Cost Variance (CV) = BCWP – ACWP
L14aS12 – Ind Asg due 7/24 Plot all the progress indicators for the time 1/1 to 9/1 Plot at .5 month intervals and use .5 month units