1 / 19

Dr. Robert M. Patty, MBA, PE Performance Improvement Facilitator / Consultant 832-717-7027 rmpatty@sb

Lean Operations for FEL and EPC. Shorten Cycle Time, Eliminate Error, Improve Quality, Reduce Cost. Dr. Robert M. Patty, MBA, PE Performance Improvement Facilitator / Consultant 832-717-7027 rmpatty@sbcglobal.net Former KBR Sr. Project Manager

booth
Télécharger la présentation

Dr. Robert M. Patty, MBA, PE Performance Improvement Facilitator / Consultant 832-717-7027 rmpatty@sb

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lean Operations for FEL and EPC Shorten Cycle Time, Eliminate Error, Improve Quality, Reduce Cost Dr. Robert M. Patty, MBA, PE Performance Improvement Facilitator / Consultant 832-717-7027 rmpatty@sbcglobal.net Former KBR Sr. Project Manager Lean-Constructability Program Manager & Consultant Lean EPC Facilitator

  2. Overview • Define leanfacility delivery service • including lean construction • Benefits and examples  • Business case • Implementation • Getting started • Key take away • Differential success • i.e. benefits using lean • Requires differential sponsorship • by executives

  3. The 20,000 ft View of Lean • Extract & align vision – top priorities • Of Client / EPC / Supplier executives • Engage employees • Of Clients / EPC / Supply chain • Extend – ultrahigh safety & quality focus • With principles and emergent change tools • To achieve downward spiraling cost & time • Different – the way the team works together • To improve performance for Clients • With mutual stakeholder benefit

  4. Traditional Project DesignBasis Project Proposal Detailed Design Bid Procurement, Fabrication & Delivery Construction Start Up ERA OS MC MC ERA OS Lean Project Delivery Project Criteria System Criteria Component Criteria Detailed Design WRLP Construction Procurement, Fabrication & Delivery Planning Construction Start Up Traditional vs. Lean Project Delivery • Assessment of initial impact on pilot projects • Major oil company, senior project managers • & value improving practices team

  5. Why – What Happens • TIC - logistics & operations savings • ~4.5% to 15% • used in balance with other VIPs • Raising task completions as planned • from 20 to 80% • Example on Mega PreFEED project • Increased national content 28% • Avoided scope growth 2.5% • Schedule-assurance avoided revenue loss 41% • Saved CAPEX 0.5% • Reduced OPEX 0.5% /year

  6. Core Performance Enhancing Strategies • Enhance • Voice-of-the-customer in decisions • Workface level productivity • Engage an emergent change tool set • Extract & manage by standards • Task-level • Manager-performer aligned • Sequence standards • For flow optimization & reliability

  7. FEL Work Package ITP – Q/A Requirements Eng. Work Package Safety Requirements Manuf. Work Package Field Work Package Construction Equipment All work should be planned in work packages developed from standards Scaffold Builds Planned Value - Manhours Timesheet Cost Code System Designation Material Status IFC Drawings Activity ID & dates 3D snap shots of work FIWP Field Installation Work Package

  8. Leadership Strategies • Transparent-status • Execution control boards • Balanced scorecards • Better fitness for outcomes • Aligned commitment • Task level operational excellence • More robust response to • Near misses • Performance breeches • Creative voices

  9. Management by Lean Work-task-level Standards Front End Planning Standards EPC Planning Standards Detailed Engineer, Procure, Construct Phase PreFEED- Appraise FEED - Select & Define Phase • If any standard does not cause • the right things to happen • consistently and reliably • it is not considered lean • It must be improved until it does • the standard itself and/or • the standard’s deployment policy • workface progress visibility & control Design Basis Project Critical Chain Schedule 4 to 6 Week moving work-task package execution plan

  10. Engineering Workface Sampling

  11. Urgency Justifies Executive Sponsorship • Alignment of work-process excellence • clients, EPC departments & supply chain • Remove comfort zone • If it doesn’t get worse • We will be ok • If it gets worse • We are victims of circumstance, still ok • Executive demand-to-improve • Render traditional cost & schedule • ‘Not-good enough’ • Figure out how to apply lean here

  12. Results of Workface Sampling Chemical Plant Construction, Jan 14-24, 2008 Non Contributory, Waiting& Non Value Added Work Direct Value Added Work 35.8% 25.2% Contributory Work 39.0%

  13. Results of Workface Sampling Chemical Plant Construction, Jan 14-24, 2008 Non Contributory, Waiting& Non Value Added Work 25.2% Effective Setup 13.5% Dismantle, 1.9% Direct Value Added Work 35.8% Fabrication & PreAssembly, 5.8% Excavating & Backfilling, 2.8% Final Assembly 11.4% Contributory Work 39.0% Placing, 0.4%

  14. Results of Workface Sampling Chemical Plant Construction, Jan 14-24, 2008 Safety Work, 3.8% Rigging & Flagging, 1.3% Non Contributory, Waiting& Non Value Added Work 25.2% Inspection & Testing; 0.5% Material and Equipment Loading, Unloading & Storage, 1.6% Clean Up, 3.2% Maintenance & Repair, 1.0% Personal Time, 1.3% Contributory Work 39.0% Move Self, 8.9% Move Tools & Materials 14.8% Locating & Positioning 2.2% Direct Value Added Work 35.8% Holding Materials or Equipment, 0.4%

  15. Results of Workface Sampling Chemical Plant Construction, Jan 14-24, 2008 Contributory Work 39.0% Idle - Crew Balance; 6.2% Idle - Interference; 2.6% Idle - Talk; 0.4% Idle - Over Manning; 2.5% Non-Contributory, Non-Value Added Work & Waiting 25.2% Idle - Late Start or Early Quit; 3.2% Idle - Discretionary; 3.2% Idle - Institutionalized Standby; 4.2% Ineffective Work; 1.5% Direct Value Added Work 35.8% Rework; 1.5%

  16. Situation-at-a-Glance Direct Tension Indicating Washer LeJeune®Bolt • Metallurgy of twist-off end • Limits bolt size • ≤ 1.125” Diameter max • Friction–dependent tension indication • Dirt or rust • Causes premature twist-off • Cannot be removed once installed • Ergonomic • Non-impact • Single side/operator installation • Operator must stop • to check washer compression • Inspector • must use feeler gage • Not ergonomic • 2 operators • Impact tool required

  17. Implementation • Visual Red Squirt Material • occurs upon advent of Proper Tension • Is just what installer needs to know • Altered metallurgy • So serrated end does not twist off Results • Installer tightens • without stopping • Inspection is Visual • or with feeler gage • Non-impacting wrench • used from one side • No size limits • reduces number of bolts • Friction independent • rust & dirt irrelevant • Easily removed • and reinstalled if needed

  18. Executive Sponsorship of Chief Improvement Officer • Differentiation now & future dominance • individuals professionally • project teams & companies • is achievable by real executive commitment • of time, resources • and intellect to learn and implement Call or send email for primer of new handbook Patty, Robert M; Denton, Michael A; Lean Operations for Front-end-loading, Engineering, Procurement, and Construction: Shorten Cycle Time, Eliminate Error, Improve Quality, Reduce Cost, Universal-Publishers, 500+ pgs, being typeset for 2009.

More Related