1 / 26

The GCC Interconnection Grid 7 th Power Transmission and Distribution Forum Kingdom of Bahrain

GCC Interconnection Authority. The GCC Interconnection Grid 7 th Power Transmission and Distribution Forum Kingdom of Bahrain. Mohamed Al-Shaikh, BSc MSc CEng MIET Manager, Maintenance - GCCIA. 28-30 October 2007. GCC Interconnection Authority. INTRODUCTION. PROJECT DESCRIPTION.

Télécharger la présentation

The GCC Interconnection Grid 7 th Power Transmission and Distribution Forum Kingdom of Bahrain

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GCC Interconnection Authority The GCC Interconnection Grid 7th Power Transmission and Distribution Forum Kingdom of Bahrain Mohamed Al-Shaikh, BSc MSc CEng MIET Manager, Maintenance - GCCIA 28-30 October 2007

  2. GCC Interconnection Authority INTRODUCTION PROJECT DESCRIPTION PROJECT STATUS LEGAL AND ORGANIZATIONAL DEVELOPMENT PROSPECTS CONCLUSIONS

  3. Interconnection Rationale

  4. Benefits of the Interconnection

  5. Sharing of the Costs of the Interconnection

  6. PROJECT DESCRIPTION

  7. Geographical Map Substations HVDC Converter Control Center

  8. Single-Line Block Diagram KUWAIT AL ZOUR 400 kV BAHRAIN 1200 MW 310 km AL FADHILI 400 kV SAUDI ARABIA SEC – ERB HDVC BACK-TO-BACK 112 km 90 km JASRA 400 kV 600 MW 1200 MW 100 km 290 km GHUNAN 400 kV QATAR DOHA SOUTH SUPER 400 kV SALWA 400 kV 150 km 750 MW 900 MW UAE SHUWAIHAT 400 kV EMIRATE NATIONAL GRID 400 MW OMAN OMAN NORTHERN GRID AL WASEET 220 kV 52 km AL OUHAH 220 kV

  9. Contract Prices

  10. PROJECT STATUS

  11. Project Progress

  12. Project Status • Completed the Submarine Cable Route Survey between Kingdoms of Bahrain and Saudi Arabia • Geo-Technical study of the Land Cable in the Kingdom of Bahrain

  13. Submarine Cable Route

  14. Project Status • Foundation work is in progress Al Jasra Doha South

  15. Project Status • Al-Fadhili Converter No. 2 & 3 – Control Building & Valve Hall constructions in progress

  16. Project Status • Al-Zour to Al-Fadhili – Hoisting of Insulators String • Salwa to Doha South – Tower Auguring of Foundation

  17. Project Status • Construction of the roof of the ICC building is in-progress • ICC – Reinforcement of Bar for Roof Beams & Slab

  18. LEGAL & ORGANIZATIONAL DEVELOPMENTS

  19. The Legal Structure / Framework for GCCIA Organizational Framework Legal Framework GCC Ministerial Committee General Agreement E & W Ministerial Committee Level Regulatory Advisory Committee General Assembly & Board Level Articles / Bylaws GCCIA Board of Directors Planning Committee Operating Committee PETA GCC Utilities Level GCCIA - CEO Transmission & Metering Codes

  20. Legal Agreements General Agreement (GA) Power Exchange & Trading Agreement (PETA) Interconnector Transmission Code (ITC) High level agreement between the Member States setting out the rules and regulations in respect of the inteconnector as well as defining the Regulatory Committee and the regulatory principles. Agreement between the Trading parties setting out the technical provisions which the Authority, the TSO Parties and the Procurement Parties will observe when operating and using the Interconnector. Agreement between the Trading parties setting out obligations in respect of installed capacities and operating reserves as well as Terms applicable to connection, use of interconnector, and Trading.

  21. PROSPECTS

  22. Development of the Electricity Market

  23. Opportunities for the GCC Electricity Market UCTE East EJLIST Arab Maghreb GCC

  24. Opportunities for the Authority

  25. Conclusions

  26. Thank you www.gccia.com.sa

More Related