The Calo Commissioning Meeting outlines the current status and future plans for the commissioning process. With a tight schedule and significant achievements, the meeting reviews installed systems for HCAL and ECAL, examining operational statuses including HV installations and PRS functionality. Current issues such as configuration problems and system statuses are discussed alongside planned milestones from February to May. The focus is on achieving a reliable detector, resolving ongoing issues, and moving towards a Linux integration for enhanced efficiency. Key goals, tasks, and software compatibility are highlighted.
E N D
ECS status and PLANS Xavier Vilasis-Cardona Calo Commissioning Meeting - Xvc
Outline • Schedule is tight and there is a lot of work to do • Achievements • Current issues • Plans Calo Commissioning Meeting - Xvc
Schedule is tight • There is a lot of work to do • Aim at a working detector • ECS to be ready to check there are no HW errors • Refine later • Commissioning weeks as milestones • 4 - 8 February • 3 - 7 March • 31 March - 4 April • 5 - 9 May Calo Commissioning Meeting - Xvc
Achievements • C-Side • HCAL DAQ – HV installed and working • ECAL DAQ – HV installed and working with some issues (see next transparency) • PRS installed • A-Side • HV projects are installed • LEDTSB boards are installed • DCS • Rack Control Project • Calo Power Supply projects • Temperature Monitoring of VFE (PS) Calo Commissioning Meeting - Xvc
Issues • CROC configuration and reset • LEDTSB – CROC • PRS-SPD • PRS project • Massive configuration problems • LED system status ? • TELL1 component problems • Should be fixed • Power Supplies • Check Alarm Action matrix • Delay times and MVPS disconnection Calo Commissioning Meeting - Xvc
Other • Integration of VFE temperature Monitoring • In the FSM • PS and SPD • Collect temperature readings in RACKs • Cooling plant ECS • New Framework components soon available Calo Commissioning Meeting - Xvc
Main Goals Calo Commissioning Meeting - Xvc
Moving to Linux • Efficiency reasons • Test PC available cadaqhv01 • Test main elements • Priority is on a working detector • Only SPECS DAQ PCs • Software Compatibility • PVSS should be OK • CAT base should be OK but needs to be checked • CAT developments • Other ? • Groups check their software on the test PC Calo Commissioning Meeting - Xvc
4FEB – Goals and Tasks I Calo Commissioning Meeting - Xvc
4FEB – Goals and Tasks II - PRS Calo Commissioning Meeting - Xvc
Move to Linux • Lower Priority Calo Commissioning Meeting - Xvc
03MAR plans • Finish any pending on the C-side • Install missing DAQ parts • Install CAT server on PVSS • If possible – evaluate the migration to linux • Test and integrate Calo Commissioning Meeting - Xvc