Plan for deliverable T11D2 - Analysis and modelling of business processes -. Final user requirements and models. Marvin meeting, Syros, 2000-09-05 Jochen Haenisch. From the project programme. Objective:
E N D
Plan for deliverable T11D2 -Analysis and modelling of business processes - Final user requirements and models Marvin meeting, Syros, 2000-09-05 Jochen Haenisch
From the project programme • Objective: • To identify and document the work processes for both virtual maritime organisations in general and the two business cases (now: scenarios) in particular • Keywords: • current workflow, weaknesses, improved workflow • process modules • WfMC • model for the web • implementation in WP2/3; validation in WP4
Previous deliverable (T11D1) • only emergency repair • selected users: • Ship Owner* • Ship Crew* • Ship Yard* • Emergency Response Service* • Classification Society* • Salvage Company (Tug Company)* • textual and graphical representation • ARIS, UML - graphics to be improved here! • Use case diagram, Sequence diagram, Collaboration diagram, Class diagram, Activity diagram
to be done • cover also planned maintenance (scenario) • cover additional users (not all required): • Insurance Company (to be done) • P&I Club (to be done) • Chartering Company • Crewing Company • Port Authority • Port State Control • Coastal State Authority • Supplier • Marine agent
Issues • T31D2 includes major process models • What else is useful? • Distribution of work
Plan • Update to ER process (compared to T31D2) - GL • textual • as-is / to-be • PM process - DNV • eEPC updates: IWi • no new roles • Summaries for actors: • insurance, P&I club - IRI Document for future use of the MEIT, not for the present one!
More contents • WfMC topic - IWi, DNV, ... • what done, what not - why • Terminology - document what is: • business scenario, business case, workflow, process, ... • What was not covered, why • Review - Neorion
Schedule • Delivery: Nov 30 • to project manager: Nov 23 • to reviewer: Nov 9 • to editor: Oct 25 • start: now
resolutions • D2 replaces D1; do not refer to the “preliminary” deliverable • both as-is and to-be description • UML or eEPC? only eEPC • What about the existing UML for ER? only eEPC there as well • explain the changes from D1 to D2 • Additional roles (not to be included in the eEPCs): • Insurance Company • P&I Club