Project Plan Review. Brian Barnett Rob Benner Alex Fleck Ryan Srogi John Keune. Discipline Leaders. Aerodynamics Propulsion Cost Analysis Rob Benner Alex Fleck Ryan Srogi Ryan Srogi Brian Barnett John Keune Structures Brian Barnett Rob Benner D&C John Keune Alex Fleck.

cate
Télécharger la présentation

Project Plan Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Plan Review Brian Barnett Rob Benner Alex Fleck Ryan Srogi John Keune

  2. Discipline Leaders AerodynamicsPropulsionCost Analysis Rob Benner Alex Fleck Ryan Srogi Ryan Srogi Brian Barnett John Keune Structures Brian Barnett Rob Benner D&C John Keune Alex Fleck

  3. Major Milestones Propulsion • Finalize weight estimate – Tues, Sept 25 • Estimate amount of thrust required – Tues, Sept 25 • Initial propeller sizing – Tues, Sept 25 • Select motor candidates based on historical data – Tues, Sept 25 • Propulsion PDR #1 – Thurs, Sept 27 • Propeller geometry selection – Mon, Oct 1 • Battery/Motor testing – Mon, Oct 8 • Final battery selection – Tues, Oct 9 • Motor/Speed controller selection – Thurs, Oct 11 • Propulsion PDR #2 – Tues, Oct 16

  4. Aerodynamics • Airfoil Selection – Thurs, Sept 27 • CL, Clmax, Drag Polar – Thurs, Sept 27 • Vertical/Horizontal Tail Selection – Thurs, Sept 27 • Aerodynamics PDR #1 – Tues, Oct 2 • Angle of Incidence – Mon, Oct 15 • 3D Analysis – Mon, Oct 15 • Aerodynamics PDR #2 – Thurs, Oct 18

  5. Structures • Spar, rib placement – Mon, Oct 1 • Theoretical structural analysis – Mon, Oct 1 • Compile material properties – Mon, Oct 1 • Material selection – Tues, Oct 2 • Gear selection/placement – Tues, Oct 2 • Wing/fuselage attachments – Wed, Oct 3 • Boom attachments – Wed, Oct 3 • Structures & Weights PDR – Thurs, Oct 4

  6. Dynamics • Block Diagram – Wed, Oct 3 • Dynamic Models – Wed, Oct 3 • Root Locus – Wed, Oct 10 • Nominal feedback gain – Wed, Oct 10 • Flow chart – Wed, Oct 10 • Dynamic Modeling PDR – Thurs, Oct 11 • Sizing of vert and horiz tails and control surfaces – Tues, Oct 17 • Aerodynamic center & center of gravity – Tues, Oct 17 • Static margin – Tues, Oct 17 • Flight Perf., Stability & Control PDR – Tues, Oct 23 Critical Design Review – Tues, Oct 30

  7. Building and Testing • Begin building – Wed, Oct 31 • Building complete – Wed, Nov 14 • Flight Readiness Review - Thurs, Nov 15 • Test Flights and Modifications – Fri, Nov 16 • First Official Flights – Tues, Nov 20