1 / 8

Network Refresh Project

Project Phases. Building Preparation Phase ? TR Renovation, PathwaysDesign Phase ? Jack analysis, Service verification with POC's.Cabling Phase ? Cable installation, termination

clarimonde
Télécharger la présentation

Network Refresh Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Network Refresh Project

    2. Project Phases Building Preparation Phase TR Renovation, Pathways Design Phase Jack analysis, Service verification with POCs. Cabling Phase Cable installation, termination & Testing. Pre-Migration Network Gear Installation & configuration. Cross Connects & port to jack mapping Migration Phase - Voice and data services migration Post Migration Activities IP Audit, Disconnect Old Gear 2

    3. Project Management Approach Scope Definition & Management Schedule Management Activity definition & sequencing Activity Resource & Duration Estimates Cost Management Cost Estimating Cost Budgeting Cost Control Quality Management (DCFS) Design Criteria/Facilities Standards, Network Guidelines Communication Management Internal & external Stakeholders Risk Management Material, Gear, Resources, Schedule, Costs 3

    4. Buildings Completed to Date (FY 09/10) Before Chemical & Nuclear Engineering (090) Energy Research Facility (223) Fraternity/Sorority Row 1 (126) Fraternity/Sorority Row 10 (135) After Talbot Hall (030) Somerset Hall (063) Worcester Hall (051) Fraternity/Sorority Row 3 (128) Fraternity/Sorority Row 8 (133) Computer & Space Sciences (224) Computer Science Instructional Center (406) 4

    5. Buildings in Progress (FY 09/10) School Of Public Health (255) Migration Phase Lefrak Hall, Animal Science & Plant Science Cabling Phase (95% complete) Pre-Migration Hornbake Library, J.M. Patterson, Francis Scott Key & Skinner Buildings Building Preparation Complete Design Phase Complete Cabling Phase intiated Mathematics, Lee, Taliaferro & Benjamin Buildings Building Preparation (80% Complete) Kick-off meetings scheduled. 5

    6. Wireless Access Point Replacement Replace all APs (QTY=2017) in Administrative & Academic buildings Project start date: Nov 30th, 2009 Replace Cisco Aironet 1130 (a/b/g standards) with Cisco AIR-LAP 1142n (a/b/g/n standards) Already replaced 1674 APs in 91 Buildings as of Jan 18th, 2010. 6

    7. Outside Plant Fiber Campus wide upgrade of Fiber backbone Project awarded to Vision Technologies start date: Dec 18th, 2009 Phase 1 Physically verify routes and cable lengths Currently Analyzing Manholes on House Drive 7

    8. Questions? 8

More Related