CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100

CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100. Prepared by: Program Management Branch (HGP) 22 September 2004 009/HGP/2004. CTA PLANNING EMBRAER PROGRAM ERJ170-200. ACTIVITIES -Total Number of Reports : 314

Télécharger la présentation

CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100 Prepared by: Program Management Branch (HGP) 22 September 2004 009/HGP/2004

  2. CTA PLANNINGEMBRAER PROGRAM ERJ170-200 ACTIVITIES -Total Number of Reports : 314 Reports for CTA review : 104 (67% delegation) (2000 m-h) Specialists Meetings : 9 weeks (2 m; PF1 availab.) (6000 m-h) -Formal CTA Meetings : 2 (2000 m-h) Support to FCAA Meetings : - Published Documents : Revisions of Doc (AFM, MRB, etc.) Pre TC Activities : 30 calendar days Coord/Flight Tests : 70 FTH (500 m-h)

  3. CTA PLANNING EMBRAER PROGRAM ERJ-170-200 SCHEDULE OF MAIN EVENTS • Application : May 2001 • Preliminary TCBM : 5 August 2003 • 1st Flight : June 2003 • Pre-flight TCBM : 10 December 2003 • AIT issuance : 23 December 2003 • Certification Flight Tests : January – September 2004 • Last Certification Reports Delivery : 30 Sept 2004 • CTA Engineering Inspection : 11 October 2004 • Final TCBM : 25 October 2004 • TC Issuance : 29 October 2004

  4. CTA PLANNINGEMBRAER PROGRAM ERJ 170-200 TOTAL REQUESTED HOURS • Total Required (CTA) : 10500 CTA AVAILABLE HOURS • Average Month : 7500 • Peak Month : 9000 • PF1 (50% availab.) : 3800/4500 Minimum period at 50% availability : 3 months

  5. CTA PLANNING EMBRAER PROGRAM ERJ-190-100 ACTIVITIES • Number of Reports : 874 (1318) • Report for CTA Review : 370 (58 % delegation) (7500m-h) • Specialists Meetings : 39 weeks (9 mo (60%); PF1 avail.) (26000 m-h) • Formal CTA Meetings : 3 (3000 m-h) • Support to FCAA Meetings : 2 (1500 m-h) • Published Documents : 1000 m-h • Pre TC Activities : 30 calendar days (3500 m-h; PF1 50% avail.) • Ground/Flight Tests : 300 FHT (2500 m-h)

  6. CTA PLANNINGEMBRAER PROGRAM ERJ-190-100 TOTAL REQUESTED HOURS • TOTAL REQUIRED (CTA) : 45000 CTA AVAILABLE HOURS • Average Month : 7500 • Peak Mont : 9000 • PF1 (50% availab.) : (3800/4500) Minimum period at 50% availability : 12 months

  7. CTA PLANNINGEMBRAER PROGRAM ERJ-190-100 SCHEDULE OF MAIN EVENTS Application : 30 May 2001 Preliminary TCBM : 2 April 2004 1st Flight : 11 February 2004 Pre-Flight TCBM : 11 August 2004 (OCTOBER 2004) AIT Issuance : 18 August 2004 (NOVEMBER 2004) Certification Flight Tests : September 24 – March 05 Last Certification Report Delivery : 13 may 2005 CTA Engineering Inspection : 8 June 2005 Final TCBM : 23 June 2005 TC Issuance : 30 June 2005