1 / 11

Cycle 17 Planning

Cycle 17 Planning. SM4, New Instruments, New Planning Elements, Changed Constraints, and a Return to 3-Gyros. LRP planning Process Flow. Planning of the different types of visits will proceed logically: GO, Survey, then emplacement of the on-COS parallel programs. Regular GO planning.

trent
Télécharger la présentation

Cycle 17 Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cycle 17 Planning SM4, New Instruments, New Planning Elements, Changed Constraints, and a Return to 3-Gyros

  2. LRP planning Process Flow • Planning of the different types of visits will proceed logically: GO, Survey, then emplacement of the on-COS parallel programs. Regular GO planning Survey program planning Parallel program planning

  3. Planning Within GO/Survey • Each of the first two categories will be broken down into two separate phases of planning: • North-point • Remainder • The purpose is to maximize utility of the underutilized orbits (which typically are the north-point, SAA-impacted orbits, and in particular the ‘heart’ orbits of the SAA).

  4. Planning Procedure • Definition: ‘Cold’ times: Generally low numbers of visits/targets which will schedule within given orbits. • Identify visits most needed for the ‘coldest’ times. This can be done in different ways • using SPIKE cold-spot tools after visits are planned). • Using the skygrid which identifies raw schedulability.

  5. Key Planning Issues • SM4 Planning • Enabling of specific instrument modes • USC generator scripts must be ready prior to ingest (q.v. wfpc2_uscs_b4_sm4.bash ringworld LRP cron) • Replacement FGS and handling guide star availability. • 2-Gyro --> 3-Gyro planning • How should we go about merging/maintaining an operational 2-Gyro LRP while simultaneously assimilating a 3-Gyro Cycle into the flow? • North-point/SAA-hiding for the new Cycle. • New SPIKE scheduling critic (not yet delivered) for restricting candidate windows. • Reserving the subset of SNAPs which are optimum for use of the North-point times. • Blackout times/angles for Bay 5/8 thermal restrictions? (depends upon result of SM4 achievements) • Power constraints for mid-2009. • New SPIKE constraint implemented with modulated orient table (not delivered yet) (ij 08-04-17 delivered with CASM 17.2 and destined for SPIKE 31.1 • Possible instrument campaigns?

  6. Key Planning Issues (2) • Identification of early-goers (find_mustgo_early.py, et.al.) • Post-LRP-build (?) emplacement of orient restrictions for any parallels (on top of COS). • Better analysis of the distribution of NICMOS and WF3/IR faint-target observations to ensure balanced SAA-hiding distribution (may not be feasible) • Change in the modulation amplitude and phase for North-point occurrences in SPIKE. • If any Survey programs are accepted, management of the proposal windows and visits is needed.

  7. LRP Planning Software Issues • Multiple scenarios for LRP build. • Metrics for deciding which LRP is superior. • Advanced target RA distribution analysis. • SPIKE hot/cold-spot analysis tools. • Apply these to both the GO pool and the Surveys • Tools to subselect and manage Survey proposals. • In Cycle 14 at the 3-->2 Gyro transition, a special procedure was required for merging the Cycle LRPs. This must be resurrected, revamped, or rewritten with modifications to handle the return to 3-Gyros.

  8. Merging 2- & 3-Gyro LRPs • In the Cycle 14 build (at the end of Cycle 13), a separate 2-Gyro constraint LRP was created and maintained with a nightly process. • Planning the ‘new cycle’ was handled with resource cut-outs and a separate set of constraints. • The 2-Gyro LRP was then merged in with the operational 3-Gyro LRP to yield the operational released LRP. • In effect, the upcoming 2-Gyro LRP was a subset of the old 3-Gyro LRP. Both could be handled within a 3-Gyro SPIKE image post-facto. • With the current and upcoming Cycle, doing the same could be similar but with a twist: • Merging a 3-Gyro LRP with a 2-Gyro LRP might be handled similarly, however, the directionality is reversed. • In planning the Cycle 17 visits, resource cut-outs from the Cycle 16- visits could be implemented (new software is needed to do this properly and not the way it was done in Cycle 14).

  9. Cycle 17 Early-Goers • Visits from the Cycle 17 pool that can execute prior to SM4 fall into 2-categories: • Singletons • Singleton visits from the current instrument suite can easily be planned to execute prior to SM4. • However, allowing planning of large numbers of these prior to the LRP build could skew the build distribution. • Linksets • These may be problematic if they have reduced 2-Gyro constraint windows for planning. Large numbers planned prior to Cycle 17 LRP build should be avoided.

  10. New/Resurrected Instruments • New Science Instruments: • COS: • A MAMA (FUV) • NUV Channel • WFC3: • IR • UVIS • Resurrected Science Instruments: • STIS: • FUV & NUV MAMAs • CCD • ACS: • WFC • HRC • Also to be installed: • FGS2: • NOBL (Bay 8) • New RSUs (back to 3 gyro ops) • New Batteries (possible new reconditioning exercises. • Also Possible: • NOBL (Bay 5)

  11. A New FGS • The new FGS will not be available for guiding for a specified period of time (needs quantification). • Incoming visits will need to be planned so as not to use this FGS post-SM4 until the expected recommisioning date. • New FGSs were accommodated after SM2 (Cycle 7) and SM3A (1999). Procedures need to be identified for handling the visit planning taking the lessons from these installations into account.

More Related