The Mu2e Working Group convenes to discuss essential project updates, including a recent meeting at Germantown. Key topics include the status of civil construction, project staffing, schedule development, and project timelines. Attendees will review staffing roles and responsibilities, emphasizing the importance of a sound work breakdown structure (WBS). Action items are outlined for follow-up, such as appointing a calorimeter manager and advancing CD-1 activities. The next meeting is scheduled for June 16, 2010.

cliff
Télécharger la présentation

Mu2e Working Group Meeting Agenda - May 19, 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mu2e Working Group Meeting May 19, 2010 1:00– 2:30 PM Snake Pit

  2. Agenda • Project Update including meeting at Germantown [Ron Ray] • Status of Civil Construction [Tom Lackowski ] • Project Staffing [Dean Hoffer] • Schedule Development Discussion [Dean Hoffer/ All] • Project Timeline [Dean and All] • Next Meeting [Dean Hoffer] • Action Items 19-May-2010 Mu2e WGM

  3. Mu2e Project Staffing (Potential Positions/Responsibilities) • Project Manager • Deputy Project Manager • Subproject Technical Managers (i.e. Level 2) • Subproject Technical Leads (i.e. Level 3) • Project Controls (Schedule and EVMS) • Project Budget Manager/ Specialist Senior/ Specialist • Project Engineers (Mechanical, Electrical/Electronics, Civil) • System Integration Engineer • Project Chemist • Project Procurement Administrator/Specialist • Project ES&H • Project Administration • Control Account Mangers (CAMs) • Project Integration Manager • Project Risk Manager • Project Configuration Manager • Project Quality Manager • NEPA Coordinator • Project Webmaster • Project Database Manager 19-May-2010 Mu2e WGM

  4. Schedule Development • Sound WBS w/Dictionary – (encompass all deliverables for entire scope of project) • Define Activities – Description (start w/verb), Durations (realistic duration, not just effort driven, target of 2 months or less) • Assign Resources – labor (in hours and include inefficiencies), material, equipment) • Define Relationships – predecessors/ successors • Develop Milestones w/Dictionary – Level 0 -?, establish schedule contingency with different level of milestone 19-May-2010 Mu2e WGM

  5. 19-May-2010 Mu2e WGM

  6. Next Meeting • Next Meeting 16-Jun, 1:00 – 2:30 PM • Next L2 Presentation? 19-May-2010 Mu2e WGM

  7. Action Items a) Get L2 Manager for calorimeter in place. – Ron Ray b) Get resources required for CD-1 activities into P6. Begin adding relationships and developing BOEs – L2s/Walter Davis c) Understand and document the magnitude of the heat shield problem – Rick Coleman d) Agree on strategy for getting tracker to CD-1 – Done e) Get moving on FE Electronics – Ron Ray 19-May-2010 Mu2e WGM